Wednesday, November 5, 2008

 

1542 TULANE AVE. :

  • The general contractor installed ceiling tiles in the conference rooms on the 6th and 7th Floors. 
  • The electrical contractor completed installing new light fixtures in the 5th, 6th and 7th Floor conference rooms and completed installation of three new recessed lights on the front porch. 
  • The sprinkler contractor installed sprinkler heads in the 6th Floor lounge. 
  • The construction cleaning contractor continued re-cleaning rooms that failed inspection on the 6th Floor and continues cleaning on the 5th Floor.     
  • Facility Services continued making minor repairs on various floors.

 

DENTAL CAMPUS AUDITORIUMS A & B RENOVATIONS:

  • The electrical contractor installed wiring for the sconces on the east and south walls in Auditorium A. 
  • The general contractor installed additional riser framing for the seating in Auditorium A and installed cementitious board at the base of the walls in Auditoriums A and B.

 

DENTAL CAMPUS 6th & 8th FLOOR LAB RENOVATIONS:

  • The electrical contractor installed wiring for electrical receptacles on the east wall of Suite 8405B and installed electrical boxes for the base cabinets in 8405A and 8405B.
  • The contractor installed sheetrock on the south wall in 8405A and installed framing for the door in the microscope room (8405E).

 

LIBRARY COMMONS:

  • The contractor installed sheetrock in the ceiling above the coffee bar.
  • LSUHSC electricians installed light fixtures along the window wall.

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:

  • The mechanical subcontractor tested the natural and medical gas in the 7th Floor lab.
    • They insulated supply duct in the bathroom on the 6th Floor, S. Prieur St. side.
    • Crews moved supply duct to install lights on the 6th Floor on the CSRB side.
    • Plumbers installed domestic water lines in the bathrooms on the 1st Floor. 
  • The iron subcontractor cleaned, ground, and finished the hand rails on the 5th and 6th Floor stairs.
    • They welded clips on the 1st Floor of the stair tower and welded safety cables on all of the platforms of the exterior stair tower.  
  • The electrical subcontractor installed outlets in the lab benches and installed can lights on the 6th Floor.
    • They moved the fire panel to the main fire room on the 2nd Floor, Bolivar side.
  • The sprinkler subcontractor moved pipe and sprinkler heads on the 6th Floor.
  • The contractor installed ceiling tiles on the 6th Floor on the CSRB side.
    • They installed door hardware on the 6th Floor CSRB side and installed floor tile in the bathroom on the 6th Floor.
    • Sheetrock was hung on the fur downs in the new lecture room on the 6th Floor.
    • Crews installed CMU walls in the bathrooms on the 1st Floor.

 

MEB 2nd FLOOR LOBBY RENOVATIONS:

  • The contractor installed columns in the Campus Office Stores area and ceiling wire in the elevator lobby.

 

MEB MDL 5 RENOVATIONS:

  • The contractor connected cables to the A/V control boxes.