Louisiana State University Health Sciences Center Administration & Finance
 

Thursday, December 11, 2008

 

1542 TULANE AVE.:

  • The general contractor completed painting in Room 545.
  • The painting contractor completed painting the front stairwell on the Claiborne Avenue end of the front hallway.
    • They completed painting Conference room 637 and started painting in Shipping and Receiving.
  • Facility Services continued making minor repairs on various floors.  

 

DENTAL CAMPUS AUDITORIUMS A & B RENOVATIONS:

  • The general contractor sanded and prepped the sheetrock at the entrances to Auditoriums A and B.
  • The electrical contractor installed conduit, wiring, and light fixtures in the electrical closet and mechanical room. 

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:

  • The electrical subcontractor continued to pull wires for the switch gear from the 1st Floor to the 2nd Floor.
  • The sprinkler contractor continued to reroute sprinkler pipe on the 6th Floor, S. Prieur/Gravier Street side.
  • The contractor painted the 6th Floor walls on the Gravier/Bolivar Street side.
    • Crews installed additional studs and sheetrock in the 2nd Floor mechanical room.
    • They finished laying floor tiles in the Men/Women bathroom on the 1st Floor, S. Prieur Street side.
    • Wall tile is being installed in the lobby area on the corner of Gravier and Bolivar Street .
    • A crew framed the wood block for the Elevators 1 and 4. 

 

LIBRARY COMMONS:             

  • The contractor installed ceiling grid in the Womans restroom.   
  • The contractor installed wood panels around the column nearest the coffee kiosk.
  • The contractor installed the coffee kiosk cooler and wall panels.     

 

MEB MDL 6 RENOVATIONS:

  • The contractor raised the steel support for the new partition track in the MDL room.
  • The contractor installed studs frame around the steel support for sound attenuation.