The general contractor completed work in Room 545 and continued installing ceiling tiles in the 4th Floor lounge and hallways.
The painting contractor continued work in the rear stairwell.
Facility Services installed four new flood lights in the rear of the building and continued making minor repairs on various floors.
DENTAL
CAMPUS AUDITORIUMS A & B RENOVATIONS:
The general contractor installed additional ceiling grid in Auditorium A.One row remains.
The electrical contractor installed additional conduit for the electrical panel power feeds.
DENTAL
6th & 8th FLOOR LABORATORY RENOVATIONS:
The general contractor installed insulation for all interior walls and sheetrock for the exterior walls in Suite 8405 .
The contractor honed the terrazzo in Room 8405A.
EXTERIOR/LANDSCAPING:
Facility Services installed irrigation lines in front of the Resource Center.
The contractor started the sidewalk construction and landscape grading at the corner of Gravier St. and S. Claiborne Ave.
LIONS/LSU
CLINIC PERMANENT REPAIRS AND MITIGATION:
The mechanical subcontractor tested water fountains and fixtures in the Womens restroom on the 6th Floor, S. Prieur St. side.
They ran pipe to the VAVs on the 6th Floor, Gravier St. side and installed return air lines on the 6th Floor, S. Prieur St. side.
The electrical subcontractor ran conduit from Panel LA6A to the 6th Floor junction box, pulled two feeders for bus duct Riser A (Bolivar side of building) on the 1st Floor to the new switchgear and installed additional cable tray on the 2nd Floor, Gravier hallway side.
The fireproofing subcontractor painted the exterior steel beams of the new stairwell, Floor 2.
The contractor painted walls on the 2nd Floor, CSRB side.
They continued to plaster the restroom and hallway on the 1st Floor, Bolivar St. /CSRB side.
Crews installed more wall tile on the 1st Floor, Roman/Bolivar side.
A crew ground down the cement in the pits of Elevator 1 and 4.
Other installed CMU in the new stairwell 1st level.
LIBRARY
COMMONS:
The contractor grouted the perimeter floor tiles in the Library.
The contractor continued installation of wood panel supports for columns.
MEB
PHARMACOLOGY LAB RENOVATIONS:
The contractor began removing old walls from the laboratory area.
MEB
2ND FLOOR LOBBY RENOVATIONS:
The contractor began installing sprinkler branch piping on the Bolivar St. side of the lobby.
MEB
MDL 6 RENOVATIONS:
The contractor continued installing piping for hot/cold water and drainage in the 3rd Floor ceiling.
RESIDENCE
HALL LOBBY EXPANSION:
The contractor removed the brick pavers under the existing mailbox room.
The contractor installed roofing insulation on the expansion.