Louisiana State University Health Sciences Center Administration & Finance
 

Wednesday, December 17, 2008

 

1542 TULANE AVE. :

  • The general contractor completed work in Room 545 and continued installing ceiling tiles in the 4th Floor lounge and hallways. 
  • The painting contractor continued work in the rear stairwell. 
  • Facility Services installed four new flood lights in the rear of the building and continued making minor repairs on various floors.

 

DENTAL CAMPUS AUDITORIUMS A & B RENOVATIONS:

  • The general contractor installed additional ceiling grid in Auditorium A.  One row remains.  
  • The electrical contractor installed additional conduit for the electrical panel power feeds.

 

DENTAL 6th & 8th FLOOR LABORATORY RENOVATIONS:

  • The general contractor installed insulation for all interior walls and sheetrock for the exterior walls in Suite 8405 . 
  • The contractor honed the terrazzo in Room 8405A.

 

EXTERIOR/LANDSCAPING:

  • Facility Services installed irrigation lines in front of the Resource Center. 
  • The contractor started the sidewalk construction and landscape grading at the corner of Gravier St. and S. Claiborne Ave.

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:

  • The mechanical subcontractor tested water fountains and fixtures in the Womens restroom on the 6th Floor, S. Prieur St. side.
    • They ran pipe to the VAVs on the 6th Floor, Gravier St. side and installed return air lines on the 6th Floor, S. Prieur St. side.
  • The electrical subcontractor ran conduit from Panel LA6A to the 6th Floor junction box, pulled two feeders for bus duct Riser A (Bolivar side of building) on the 1st Floor to the new switchgear and installed additional cable tray on the 2nd Floor, Gravier hallway side.  
  • The fireproofing subcontractor painted the exterior steel beams of the new stairwell, Floor 2.
  • The contractor painted walls on the 2nd Floor, CSRB side.
    • They continued to plaster the restroom and hallway on the 1st Floor, Bolivar St. /CSRB side.
    • Crews installed more wall tile on the 1st Floor, Roman/Bolivar side.
    • A crew ground down the cement in the pits of Elevator 1 and 4.
    • Other installed CMU in the new stairwell 1st level.

 

LIBRARY COMMONS:       

  • The contractor grouted the perimeter floor tiles in the Library.   
  • The contractor continued installation of wood panel supports for columns.

 

MEB PHARMACOLOGY LAB RENOVATIONS:

  • The contractor began removing old walls from the laboratory area. 

 

MEB 2ND FLOOR LOBBY RENOVATIONS:

  • The contractor began installing sprinkler branch piping on the Bolivar St. side of the lobby.

 

MEB MDL 6 RENOVATIONS:

  • The contractor continued installing piping for hot/cold water and drainage in the 3rd Floor ceiling.

 

RESIDENCE HALL LOBBY EXPANSION:

  • The contractor removed the brick pavers under the existing mailbox room. 
  • The contractor installed roofing insulation on the expansion.