Louisiana State University Health Sciences Center Administration & Finance
 

Wednesday, December 3, 2008

 

1542 TULANE AVE. :

  • The electrical contractor continued installing new light fixtures in the conference rooms on the 2nd and 3rd Floors.
  • The elevator contractor continued removing the protective film from Elevator 3.  
  • The general contractor continued drywall taping and preparation in Room 545.
  • The painting contractor continued painting the front stairwell on the Charity end of the hall.
  • The network wiring contractor continued wiring new drops on the 5th Floor. 
  • Facility Services sealed old exhaust duct wall penetrations on the exterior walls facing the Lakeside Lot and continued making minor repairs on various floors. 
  • Electricians ran new conduit for additional exterior lighting that will be installed at the rear of the building.

 

DENTAL CAMPUS AUDITORIUMS A & B RENOVATIONS:

  • The contractor completed the concrete finishing work for the stairs in Auditorium B.
  • The mechanical contractor installed the drain line to the AHU for Auditorium B.

 

DENTAL 6th & 8th FLOOR LABORATORY RENOVATIONS:

  • The electrical contractor connected wiring for the junction boxes above the ceiling in Suite 8405 .

 

EXTERIOR/LANDSCAPING:

  • LSUHSC Facility Services crews performed landscape maintenance around the downtown campus.

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:

  • The mechanical subcontractor installed more thermostats on the 6th Floor.
    • They continued demolishing ductwork and water pipes in the 6th Floor lab and glass pipe on the 2nd Floor.
    • Heating hot water and chilled water pipes on the Bolivar St. side of the 1st Floor are being insulated.
  • The electrical subcontractor continued to remove the old conduits in the 6th Floor lab.
    • They ran conduit to ATS 1 and 2 from the 2nd Floor to the new switchgear and installed conduit for the lights and exhaust fans in the stairwell. 
  • The sprinkler subcontractor installed stand pipe in the stairwell sprinklers. 
  • The contractor taped and floated sheetrock in the 6th Floor simulation rooms.
    • Crews installed metal studs and sheetrock for the fur down on the S. Prieur/Gravier St. side of the 6th Floor.
    • They also installed metal studs and sheetrock on the 2nd Floor and metal lathe on the 1st Floor.
    • The CMU wall on the 1st Floor is being plastered.
    • Wall tile is being installed in the restrooms on the 1st Floor.
    • They pressure washed the new stairwell.

 

LIBRARY COMMONS:       

  • LSU electricians installed light fixture supports in the ceiling near the windows.

 

MEB 2ND FLOOR LOBBY RENOVATIONS:

  • The sprinkler subcontractor installed sprinkler pipe on the Roman St. side of the lobby.

 

MEB MDL 6 RENOVATIONS:

  • The contractor removed the remaining VCT tiles from the main MDL room.
  • They finished capping existing plumbing below the floor in the main MDL room.
  • Existing receptacles in the main MDL room were disconnected and capped.
  • The contractor de-installed the existing LCD panels and projector screens from the main MDL room.

 

RESIDENCE HALL LOBBY EXPANSION:

  • The contractor removed the existing frame where the temporary wall was built and installed two vertical frames near the double sliding door.