The general contractor continued painting in Room 545 and installed ceiling tiles in the 5th Floor lounge.
The moving contractor delivered furniture and contents for the Dermatology and Anesthesiology departments to their offices on the 6th Floor.
The painting contractor continued painting the front stairwell on the Claiborne Avenue end of the front hallway.
The terrazzo contractor completed cove base repairs in the front hallways on the 4th through the 7th Floors.
Facility Services continued minor repairs on various floors.
DENTAL
CAMPUS AUDITORIUMS A & B RENOVATIONS:
The general contractor installed the entrance door frame to Auditorium A and cut an opening for a new door in Room 4205.
The mechanical contractor installed diffusers and flex duct in Auditorium B.
DENTAL
CAMPUS 6TH AND 8TH FLOOR LAB RENOVATIONS:
The general contractor extended the corridor wall framing to the slab of the deck above.
The contractor applied additional water-proofing mastic to the exterior walls.
EXTERIOR/LANDSCAPING:
Facility Services continued adjusting landscape edging in the planting beds in front of the Resource Center .
LIONS/LSU
CLINIC PERMANENT REPAIRS AND MITIGATION:
The mechanical subcontractor installed additional storm drain pipe in the new stairwell and removed existing plumbing piping on the 6th Floor, S. Prieur/Gravier Street side.
The sprinkler contractor rerouted sprinkler piping on the 6th Floor, S. Prieur/Gravier Street side.
The contractor taped and floated sheetrock on the 6th Floor, S. Prieur/Gravier Street side.
They primed the 6th Floor walls on the Gravier/Bolivar Street side and painted marker boards on the Perdido Street side.
Crews installed studs and sheetrock in the 2nd Floor electrical room and plastered the 1st Floor CMU wall on the S. Prieur Street side.
LIBRARY
COMMONS:
The contractor laid additional floor tiles at the Library entrance.
The contractor installed wood supports around two columns for the column covers and install the doorframes for the restrooms.
MEB
2ND FLOOR LOBBY RENOVATIONS:
The contractor installed the knife edge ceiling grid trim on the South Roman Street side.
MEB
MDL 6 RENOVATIONS:
The contractor raised the steel support for the new partition track in the MDL room.
RESIDENCE
HALL LOBBY EXPANSION:
The contractor installed five vertical mullions above the entrance of the Residence Hall.
The contractor taped and floated the interior temporary wall.