The general contractor continued taping and sanding the drywall in Room 443 and began taping and mudding the drywall in Room 345.
They continued patching holes on the 2nd and 3rd Floor and the construction of new walls in the 2nd Floor lounge.
Facility Services installed the sink, refrigerator and the ice machine in the 4th Floor lounge kitchenette and continued installing door hardware on the 3rd and 4th Floors.
DENTAL
CAMPUS AUDITORIUMS A & B RENOVATIONS:
The electrical contractor installed the down lights in Auditorium A.
DENTAL
6th & 8th FLOOR LABORATORY RENOVATIONS:
The contractor finished installing sheetrock around doorways and service utilities in Room 8405A, 8405D, 8405E, 8405F, 8405G and 8405J.
EXTERIOR/LANDSCAPING:
The contractor continued installing sprinkler piping and edging in the lot at the corner of S. Claiborne Ave. and Gravier St .
Facility Services mulched and cleaned the planting beds in front of the Allied Health/Nursing Building.
LIONS/LSU
CLINIC PERMANENT REPAIRS AND MITIGATION:
The mechanical subcontractor installed and insulated supply duct on the Bolivar St. side of the 6th Floor.
The electrical subcontractor installed lights in the 6th Floor large lecture room and continued roughing in electrical conduit in the old laboratory space.
The sprinkler subcontractor installed sprinkler heads in the center of the 6th Floor.
The contractor installed studs for fur downs on the 6th Floor, Bolivar Street Side.
They plastering above the doorframe on the Gravier St./Bolivar St. side of the 1st Floor and continued fireproofing the beams on the 1st through 6th Floors of the stairwell.
LIBRARY
COMMONS:
The contractor continued install branch ductwork in the small multi media room.
LSUHSC electricians installed light fixtures in the coffee kiosk.
MEB
2ND FLOOR LOBBY RENOVATIONS:
The flooring contractor began installing tile base.
MEB
PHARMACOLOGY LAB RENOVATIONS:
The general contractor continued to frame walls inside the laboratory area.
RESIDENCE
HALL LOBBY EXPANSION:
The contractor continued installing stud frames for the fur-down along the diffusers between Tower A & B.
The contractor installed spandrel glass on Perdido Street side.