The general contractor installed drywall for Room 443, continued paint removal in the auditorium, installed a new wall in Room 345 and continued patching holes on the 3rd Floor.
The flooring contractor set-up for carpet installation on the 4th Floor.
The painting contractor completed painting the center stairwell from the 5th to 8th Floor.
Facility Services continued installing door stops, adjusting doors, and installing new room numbers on the 4th Floor.
DENTAL
6th & 8th FLOOR LABORATORY RENOVATIONS:
The mechanical contractor installed the supply duct outlet taps for the ductwork in 8405A.
EXTERIOR/LANDSCAPING:
Facility Services installed the landscape edging, continued finish grading and continued installing plants in front of the Resource Center .
LIONS/LSU
CLINIC PERMANENT REPAIRS AND MITIGATION:
The mechanical subcontractor completed installing and tested new chilled water lines to the 1st Floor AHU on the Bolivar Street side.
The electrical subcontractor installed the first floor buss duct tap on the Bolivar Street side.
The sprinkler subcontractor installed sprinkler heads on the 6th Floor, Bolivar Street side.
The contractor installed studs on the 6th Floor, Gravier Street side.
They installed ceiling grid on the 6th Floor in the center hallway and continued fireproofing the beams on the 4th – 6th Floors of the new exterior stairwell.
LIBRARY
COMMONS:
The contractor continued installing custom column covers.