The general contractor continued removing old paint in the auditorium, patching holes on the 2nd and 3rd Floors, and installing drywall in Room 443.
They began working on the build-out of the 2nd Floor lounge.
Facility Services continued removing old striping in the Lakeside Lot.
EXTERIOR/LANDSCAPING:
Facility Services completed installing plants and spreading mulch in front of the Resource Center .
LIONS/LSU
CLINIC PERMANENT REPAIRS AND MITIGATION:
The mechanical subcontractor installed heating hot water lines to the 6th Floor, Bolivar Street Side VAV.
They installed supply duct on the Bolivar St. side of the 6th Floor.
A crew insulated chill water lines is the same area.
Fixtures were installed on the 1st Floor, S. Prieur Street side.
The electrical subcontractor roughed in junction boxes on the 6th Floor, Bolivar Street side and installed light fixtures in the hallway between the simulation rooms on the 6th Floor.
The sprinkler subcontractor installed sprinkler heads on the 6th Floor, Bolivar Street Side between the simulation rooms.
The contractor completed installing access panels on the S. Prieur Street side of the 3rd and 7th Floors.
A crew installed studs on the 6th Floor, Gravier/Bolivar Street Side.
Others installed wall tile on the 1st Floor, S. Prieur Street side.
They continued fireproofing the beams on the 1st through 6th Floors of the exterior stairwell.
LIBRARY
COMMONS:
Work continued on the installation of the custom wood column covers.
Branch HVAC ductwork was installed in the large multimedia room.
New sprinkler heads have been installed in the window seating area and the multimedia rooms.
MEB
2ND FLOOR LOBBY RENOVATIONS:
The flooring contractor continued installing floor tile on the Bolivar Street side.
MEB
PHARMACOLOGY LAB RENOVATIONS:
The electrical subcontractor continued demolition and started running new conduit in the laboratory area.
The general contractor removed construction debris.
MEB
MDL 6 RENOVATIONS:
The contractor installed ceiling grid in the main MDL room and installed sheetrock for the partition storage room.
RESIDENCE
HALL LOBBY EXPANSION:
The contractor began the installation of new ceiling grid in the lobby between Towers A and B.