The furniture vendor wiped down furniture in the offices on the 4th Floor.
The mechanical contractor continued piping new fan coil units on the 2nd and 3rd Floors.
The network wiring contractor continued installation of new network wiring on the 1st Floor.
Facility Services continued painting offices and hallways on the 4th Floor.
They installed new doors on the freight elevator lobby and installed two exterior lights adjacent to the Shipping and Receiving entrance.
DENTAL
6th & 8th FLOOR RENOVATIONS:
The electrical contractor installed bulbs for the new light fixtures and cover plates for light switches and duplex receptacles in Rooms 6333 and 6335.
The contractor installed the power feed for the exhaust fan motor that will be installed on the roof.
The painting contractor touched up the paint on the walls and door frames in Suite 8405A - 8405K.
EXTERIOR/LANDSCAPING:
Contractor placed concrete footers for the new fence at the corner of Gravier St. and S. Claiborne Ave. and placed a section of the new sidewalk by the District Energy Garage elevator entrance on Gravier St .
LIONS/LSU
CLINIC PERMANENT REPAIRS AND MITIGATION:
The contractor installed curtain wall mullions on the 2nd Floor of the new exterior stairwell.
The contractor continued to install restroom partitions in the Womens restroom on the 6th Floor, S. Prieur Street side.
Their crews continued installing window frames in the 6th Floor simulation room on the Bolivar St. side and installing sheetrock in the 6th Floor elevator lobby.
The mechanical subcontractor insulated additional supply duct and chilled water valves in the mechanical room on the 6th Floor.
They continued installing fire dampers on the 2nd Floor.
LIBRARY
COMMONS:
The contractor painted the walls the main study area and primed walls in the multi-media rooms.
LSU electricians installed additional light fixtures above the coffee kiosk.
MEB
MDL 6 RENOVATIONS:
The contractor completed installing VCT tiles in the main MDL room.
MEB
PHARMACOLOGY LAB RENOVATIONS:
The general contractor continued hanging sheetrock in the administrative area.
The electrical contractor continued to pull wire and run conduit in the laboratory area.
The mechanical contractor installed waste water pipes below the laboratory area.
MEB
2nd FLOOR LOBBY RENOVATIONS:
The contractor continued installing steel frame for the exterior sliding glass door on the Bolivar St. side of the lobby.
RESIDENCE
HALL LOBBY EXPANSION:
The interior contractor continued installing ceiling grid in the lobby between the A & B Towers .
Crews continued installing sheetrock, taping and floating in the Perdido St./Bolivar St. corner of the lobby.
The mechanical contractor continued installing hard duct for the diffusers in the extended lobby area.
RESIDENCE
HALL WALKWAY RESURFACING
The contractor painted the final coat on the underside of the walkway.