  • The furniture vendor wiped down furniture in the offices on the 4th Floor.
  • The mechanical contractor continued piping new fan coil units on the 2nd and 3rd Floors.
  • The network wiring contractor continued installation of new network wiring on the 1st Floor. 
  • Facility Services continued painting offices and hallways on the 4th Floor.
    • They installed new doors on the freight elevator lobby and installed two exterior lights adjacent to the Shipping and Receiving entrance.

 

DENTAL 6th & 8th FLOOR RENOVATIONS:

  • The electrical contractor installed bulbs for the new light fixtures and cover plates for light switches and duplex receptacles in Rooms 6333 and 6335. 
  • The contractor installed the power feed for the exhaust fan motor that will be installed on the roof. 
  • The painting contractor touched up the paint on the walls and door frames in Suite 8405A - 8405K.

 

EXTERIOR/LANDSCAPING:

  • Contractor placed concrete footers for the new fence at the corner of Gravier St. and S. Claiborne Ave. and placed a section of the new sidewalk by the District Energy Garage elevator entrance on Gravier St . 

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:        

  • The contractor installed curtain wall mullions on the 2nd Floor of the new exterior stairwell.    
  • The contractor continued to install restroom partitions in the Womens restroom on the 6th Floor, S. Prieur Street side.
    • Their crews continued installing window frames in the 6th Floor simulation room on the Bolivar St. side and installing sheetrock in the 6th Floor elevator lobby.
  • The mechanical subcontractor insulated additional supply duct and chilled water valves in the mechanical room on the 6th Floor.
    • They continued installing fire dampers on the 2nd Floor.

 

LIBRARY COMMONS:

  • The contractor painted the walls the main study area and primed walls in the multi-media rooms. 
  • LSU electricians installed additional light fixtures above the coffee kiosk.

 

MEB MDL 6 RENOVATIONS:

  • The contractor completed installing VCT tiles in the main MDL room.

 

MEB PHARMACOLOGY LAB RENOVATIONS:

  • The general contractor continued hanging sheetrock in the administrative area. 
  • The electrical contractor continued to pull wire and run conduit in the laboratory area. 
  • The mechanical contractor installed waste water pipes below the laboratory area. 

 

MEB 2nd FLOOR LOBBY RENOVATIONS:

  • The contractor continued installing steel frame for the exterior sliding glass door on the Bolivar St. side of the lobby.

 

RESIDENCE HALL LOBBY EXPANSION: 

  • The interior contractor continued installing ceiling grid in the lobby between the A & B Towers .
    • Crews continued installing sheetrock, taping and floating in the Perdido St./Bolivar St. corner of the lobby.   
  • The mechanical contractor continued installing hard duct for the diffusers in the extended lobby area.

 

RESIDENCE HALL WALKWAY RESURFACING

  • The contractor painted the final coat on the underside of the walkway.
  • The project is now complete.