The general contractor continued patching and taping the walls in Rooms 109H, 111 and 111A.
They completed installing the new suspended ceiling grid in Room 109H.
The demolition in Room 341, 342 and 343 is proceeding.
The mechanical contractor continued installing new fan coil units on the 3rd Floor.
The painting contractor continued painting offices on the 3rd Floor and the center stairwell between the 1st and the 4th Floors.
The glass contractor installed the new storefront in the 1st Floor lounge and continued trim work.
Facility Services continued making repairs on the 1st, 2nd and 3rd Floors, painting hallways on the 3rd Floor, and connecting electrical service for fan coil units on the 3rd floor.
They began installing the new ceiling grid in Room 319C.
LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:
The electrical contractor pulled control wire from the roof mounted emergency generator to the 2nd Floor.
They continued installing light fixtures in the 6th Floor computer lounge.
The contractor continued removing shaft walls from around the freight elevator.
The installation of the glass on the exterior stairwell has been completed.Crews have begun caulking the glass panels.
Workers continued installing granite on the exterior of the new stairwell.
Ceiling tile was installed in the 6th Floor elevator lobby.
Crews continued installing the wall by the roll down fire door on the 6th Floor.
They have started installing sheet vinyl in the simulation labs.
The granite floors on the 1st Floor, Bolivar Street side are being stripped.
The mechanical contractor mounted actuators on the 1st and 6th Floors in the mechanical rooms on the S. Prieur Street side.
They capped the fuel lines on the roof and on the 1st Floor.
The sprinkler subcontractor continued installing sprinkler heads on the 6th Floor in the computer lounge.
LIBRARY COMMONS:
The contractor continued to paint the composite wall panels in the large multimedia room and installed sheetrock inside the Library.
Additional work was done on the new display case in the elevator lobby.
Facility Services continued installing light switches.
MEB 2nd FLOOR LOBBY RENOVATIONS:
The contractor continued installing the new light fixtures.
MEB MDL #6 RENOVATIONS:
The contractor installed countertops, chase covers, and casework panels.
MEB PHARMACOLOGY LAB RENOVATIONS:
The contractor installed additional ceiling grid in the administrative area.
They installed exhaust ductwork between the administrative area and the exhaust chase.
RESIDENCE HALL LOBBY EXPANSION:
The contractor continued installing air conditioning plenum boxes and linear diffusers.
Ceiling grid was installed in the back lobby area in the C Tower.
The contractor began running fire alarm wires.
DENTAL
6th& 8th FLOOR LAB RENOVATIONS
The cabinet installers installed the wall-mounted and peninsula shelving in Suite 8405 .
The network wiring crew installed the network wiring for the peninsulas in 8405A and 8405B.
They installed the network drops and wall plates for Rooms 6333 and 6335.
The plumbing contractor installed the gas and vacuum connections for the peninsulas in Rooms 8405A and 8405B.
DENTAL SCHOOL AUDITORIUM A &
B RENOVATIONS
The contractor primed and painted the wing walls in Auditoriums A & B.
DENTAL SCHOOL BOILER INSTALATION
The contractor installed the gas piping and valves for the boiler.
They assembled and prepped the boiler connections for the scheduled system tie-in.