The general contractor continued patching and taping the walls in Rooms 109H, 111 and 111A, and started installing the new suspended ceiling grid in Rooms 111 and 111A.
The electrical contractor began the electrical rough-in in the 1st Floor lounge.
The glass contractor continued installing the trim on the new storefront in the 1st Floor lounge.
The mechanical contractor continued installing new fan coil units on the 3rd Floor.
The painting contractor started patching offices on the 2nd Floor.
They completed painting the center stairwell between the 1st and the 4th Floors.
LSUHSC Facility Services continued making repairs on the 1st, 2nd and 3rd Floors and connecting electrical service for fan coil units on the 3rd Floor.
They completed installing the new ceiling grid in Room 319C.
EXTERIOR/LANDSCAPING:
LSUHSC Facility Services completed planting shrubs and mulching in the rear of the Resource Center along Gravier St .
LIONS/LSU
CLINIC PERMANENT REPAIRS AND MITIGATION:
The electrical contractor installed the annunciator panels on the 1st and 2nd Floors.
They pulled feeder wires from the fire pump motor and jockey pump to the fire pump controller on the 2nd Floor.
Crews continue to pull control wire from the roof top generator to the ATS and install light fixtures in the 6th Floor computer lounge.
The contractor prepped the freight elevator for the new flood wall.
A crew began installing cabinets for the reception desk on the 6th Floor.
Others began installing ceramic border tile in the 6th Floor computer lounge.
They continue installing exterior granite on the new stairwell and caulking the glass panels.
Additional ceiling tile was installed on the 6th Floor.
The sheet vinyl for the floors in the simulation labs is being laid.
A crew began installing VCT in the hallway.
They continued stripping the granite floors on the 1st Floor, Bolivar Street side.
The mechanical contractor removed the acid waste line above the new switchgear.
They continued installing supply and return grilles in the 6th Floor computer lounge.
The sprinkler subcontractor continued installing sprinkler heads in the 6th Floor computer lounge.
LIBRARY
COMMONS:
The contractor continued to paint the composite wall panels in the large multimedia room and installing sheetrock in the library.
The contractor installed glass in the display case in the elevator lobby.
Facility Services installed a transfer switch for emergency lighting and installed drains for the coffee kiosk.
MEB
2nd FLOOR LOBBY RENOVATIONS:
The contractor continued installing light fixtures.
LSUHSC Facility Services re-routed pneumatic lines so they will not be in the open ceiling area.
MEB
PHARMACOLOGY LAB RENOVATIONS:
The contractor installed additional ceiling grid in the administrative area.
The contractor installed new exhaust ductwork in the corridor.
RESIDENCE
HALL LOBBY EXPANSION:
The contractor began framing the fur down in back lobby area in Tower A.
Crews continued installing ceiling grid in the back lobby area in Tower C.
Additional fire alarm wires were run between the A & B tower lobby areas.
The enclosure contractor installed the single sliding door on the Bolivar St. /Perdido St. side.
DENTAL
6th & 8th FLOOR LAB RENOVATIONS:
The contractor installed the remaining base cabinets for the peninsulas in Suite 8405A .
The network wiring crew installed the network wiring in Rooms 8405C, 8405D, 8405E, 8405F, and 8405G and tested the network drops for Rooms 6333 and 6335.
The plumbing contractor installed sink connections (hot water, cold water, and drain) for the sinks in Rooms 8405C, 8405D, and 8405E.
DENTAL
BOILER INSTALLATION:
The contractor completed the connection of the new boiler and insulated the steam line.