  • The general contractor painted in Room109H and continued drywall and ceiling work in Rooms 111 and 111A.
  • The electrical contractor continued the electrical rough-in in the 1st Floor lounge.
  • The glass contractor completed installation and trim work of the new glass wall in the 1st Floor lounge.
  • The painting contractor began painting offices on the 2nd Floor.
  • Facility Services continued making miscellaneous repairs on the 1st Floor and installing thermostats for fan coil units on the 3rd Floor.

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:

  • The contractor installed concrete forms for the freight elevator flood proofing wall.
    • Workers continued installing exterior granite on the 2nd level of the new stairwell.
    • They installed carpet in the large conference room and installed ceiling tile on the 6th Floor, Bolivar/Gravier Street side.
  • The mechanical contractor soldered the pipes for the medical air/gas/vacuum ceiling boxes in the simulation rooms.
  • The sprinkler subcontractor is installing sprinkler heads in the Directors office.
  • The electrical contractor pulled wire from the jockey pump to panel AC2A.

o      They installed exit signs in the 6th Floor computer lounge area.

 

LIBRARY COMMONS:

  • The contractor continued installing ceiling baffles.
  • Two additional custom furniture bases were installed in the study area.

 

MEB 2nd FLOOR LOBBY RENOVATIONS:

  • The contractor continued installing light fixtures.

 

MEB PHARMACOLOGY LAB RENOVATIONS:

  • The contractor painted walls in the administrative area.
  • The contractor modified sprinkler heads in the lab area.

 

RESIDENCE HALL LOBBY EXPANSION: 

  • The contractor continued framing the fur down in the back lobby area of Tower A.
  • They removed power and access control devices from the old entrance.

 

DENTAL 6th & 8th FLOOR RENOVATIONS:

  • The cabinet installers installed the backsplash for the peninsulas in Suites 8405A and 8405B.
  • The network wiring crew installed the network wiring in Rooms 8405H, 8405I, and 8405J. 
  • The electrical contractor installed receptacles for the peninsulas in 8405A and 8405B.