The general contractor continued painting in offices on the 3rd Floor and began painting in Room 109H.
The mechanical contractor continued installing new fan coil units on the 3rd Floor.
The painting contractor continued painting offices on the 3rd Floor.
Facility Services continued making repairs on the 1st and 3rd Floors, painting hallways on the 3rd Floor, and connecting electrical service for the new fan coil units.
EXTERIOR/LANDSCAPING:
LSUHSC Facility Services planted shrubs in the rear of the Resource Center .
LIONS/LSU
CLINIC PERMANENT REPAIRS AND MITIGATION:
The contractor installed ceiling tile on the Gravier St. side of the 6th Floor.
A crew continued installing the wall around the new roll up fire door on the 6th Floor/
Another crew is installing CMU walls on the Bolivar St. side of the 1st Floor.
The exterior glass is being installed on the exterior of the new stairwell.
The mechanical contractor continued installing the diesel fuel pipes on the 1st Floor, CSRB side.
They continue to install the supply and return grilles on the Gravier St. side of the 6th Floor.
The electrical contractor installed wires from the disconnects to the roof mounted emergency generator.
They ran conduit to the battery charger and the heater for the generator on the roof.
Electricians installed exit signs, strobes and speakers on the CSRB side of the 6th Floor.
They installed the VFD on the 6th Floor in the Bolivar St. side mechanical room and tied in the fire phones on the 6th Floor.
The sprinkler contractor installed sprinkler heads on the 6th Floor, Gravier St. side.
AT&T began pulling the main telephone feeder cable.
LIBRARY
COMMONS:
The contractor installed window shades.
They continued to paint the composite wall panels in the small multimedia room and began installing the wooden ceiling trim in the study area.
The contractor continued installing the display case in the elevator lobby and near the stairs.
MEB
2nd FLOOR LOBBY RENOVATIONS:
The contractor began installing granite on the columns.
They installed the door frames on the north side of the lobby.
MEB
MDL 6 RENOVATIONS:
The A/V contractor completed programming and testing the new audio/video components.
The contractor connected drains to the eight sinks.
MEB
PHARMACOLOGY LAB RENOVATIONS:
The contractor is painting walls in the administrative area.
RESIDENCE
HALL LOBBY EXPANSION:
The contractor laid the final mortar bed layer in the two corner lobby areas.
The enclosure contractor installed break metal on the underside of the roof above the entrance door.
The interior contractor continued framing and installing sheetrock for the fur down in the expanded lobby area.
DENTAL
SCHOOL A and B AUDITORIUM RENOVATIONS
The contractor taped and floated the new (smaller) wing walls in both auditoriums.
DENTAL
6th & 8th FLOOR LAB RENOVATIONS:
The contractor installed base cabinets and shelving in the large rooms on the 8th Floor.
ALLIED
HEALTH/ NURSING ROOF REPLACEMENT
Work has begun on the project.The contractor is removing the old ballast (gravel) from the roof.