The general contractor painted the walls in Rooms 341, 342, and 343.
They continue installing drywall in the 1st Floor lounge.
The electrical contractor is installing wiring for ceiling lights in the 1st Floor lounge.
The State Elevator Inspector cleared the final items on Elevators 1, 2 and 3 and certified them for normal use.
The furniture vendor installed desks and file cabinets in Room 111.
The network wiring contractor continued installing new drops in Rooms 111 and 111A.
LSUHSC Facility Services electricians continue making miscellaneous electrical repairs on the 1st and 2nd Floors.
LIONS/LSU
CLINIC PERMANENT REPAIRS AND MITIGATION:
The contractor finished installing wall covering in the computer lounge.
Workers are installing additional glass in the stairwell.
They are touching up paint throughout the 6th Floor.
Room signs are being installed on the 6th Floor.
Sprinkler heads are being installed on the Gravier St. side of the 6th Floor.
Crews installed tile floor on the Bolivar St. side of the 1st Floor.
Granite pavers are being laid around the new stairwell.
Painters primed the CMU walls of the mechanical rooms, electrical rooms, and stairwells on the 1st Floor.
The electrical contractor trimmed out and tested the fire alarm devices on the 6th Floor.
They installed lights in the 1st Floor restrooms and receptacles on the Prieur St. side of the 1st Floor.
Conduit was run from the 6th Floor to the 2nd Floor demark (telephone) room for the 200 pair cable.
Conduit was run for the sump pump in the freight elevator.
LIBRARY
COMMONS:
The contractor installed ceiling trim above the coffee kiosk.
LSUHSC electricians installed light fixtures near the decorative screens and installed the faceplates for the network drops.
MEB
PHARMACOLOGY LAB RENOVATIONS:
The casework contractor hung overhead shelves.
The contractor hooked up plumbing underneath the casework in Room 5219.
VCT was installed in the administrative area.
ALLIED
HEALTH/NURSING RE-ROOFING:
The contractor removed debris from the roof.
RESIDENCE
HALL LOBBY EXPANSION:
The interior contractor continued taping and floating the fur down in the expanded lobby area.
Ceiling tiles are being installed between the A & B Tower lobbies.
DENTAL SCHOOL
AUDITORIUM A & B RENOVATIONS:
The electrical contractor installed additional conduit in the elevator lobby extending into the crosswalk.This will support the Creative Presentations equipment installation.