Louisiana State University Health Sciences Center Administration & Finance
 

Thursday, April 2, 2009

 

NOTICE:  On Friday, April 3rd, from 6:00 PM to midnight, there will be a Nitrous Oxide and Oxygen outage at the Dental School Clinic Building , so that the gas valve connections on the 2nd floor can be checked for obstructions.

 

1542 TULANE AVE. :

  • The general contractor continued hanging drywall in Rooms 341, 342 and 343.
    • They began painting the 2nd Floor lounge.
    • Workers completed painting in Rooms 235K and 235M.
  • The mechanical contractor continued installing the new fan coil unit in Room 345A.
  • The network wiring contractor continued installation of new data drops on the 3rd Floor.
  • The roll-up door contractor is proceeding with the installation of the new parking garage roll-up door.
  • Facility Services continued painting and making electrical repairs on the 1st and 3rd Floors.

 

EXTERIOR/LANDSCAPING:

  • LSUHSC Facility Services continued planting shrubs in the rear of the Resource Center along S. Prieur St .

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:

  • The contractor placed floor tile in the rear of the building and continued plastering the soffit. 
  • The electrical contractor continued to connect wire to the Stryker equipment.
    • Workers continue to remove old feeder cable in the switchgear room.
  • Stryker continues to install A/V equipment in the simulation rooms. 
  • AT&T continues telephone feeder installation. 

 

LIBRARY COMMONS:

  • The contractor completed work on the custom furniture and display cases. 
  • Facilities Services electricians installed light switches in the multimedia rooms.   

 

MEB 2nd FLOOR LOBBY RENOVATIONS:

  • The contractor installed sheetrock near the granite columns. 

 

MEB PHARMACOLOGY LAB RENOVATIONS:

  • The contractor completed installing light fixtures in the administrative area.
  • Workers began installing the peninsular casework in Room 5219.
  • A crew installed black tile around the doorways in the administrative area.

 

RESIDENCE HALL LOBBY EXPANSION:

  • The interior contractor installed sheetrock and taped and floated the fur down in the mezzanine level between the B & C Towers .
  • The contractor continued framing for the hard ceiling in the expanded lobby area.

 

ALLIED HEALTH/NURSING RE-ROOFING:

  • No work due to rain and high winds. 

 

DENTAL SCHOOL AUDITORIUMS A & B RENOVATIONS:

  • The electrical contractor installed additional overhead conduit for the podium, speaker, and projector connections in Auditorium B, extending the conduit into the lobby area.