NOTICE:On Friday,
April 3rd, from 6:00 PM to midnight, there will be a Nitrous Oxide and Oxygen
outage at the Dental School Clinic Building , so that the gas
valve connections on the 2nd floor can be checked for obstructions.
1542 TULANE AVE. :
The general contractor continued hanging drywall in Rooms 341, 342 and 343.
They began painting the 2nd Floor lounge.
Workers completed painting in Rooms 235K and 235M.
The mechanical contractor continued installing the new fan coil unit in Room 345A.
The network wiring contractor continued installation of new data drops on the 3rd Floor.
The roll-up door contractor is proceeding with the installation of the new parking garage roll-up door.
Facility Services continued painting and making electrical repairs on the 1st and 3rd Floors.
EXTERIOR/LANDSCAPING:
LSUHSC Facility Services continued planting shrubs in the rear of the Resource Center along S. Prieur St .
LIONS/LSU
CLINIC PERMANENT REPAIRS AND MITIGATION:
The contractor placed floor tile in the rear of the building and continued plastering the soffit.
The electrical contractor continued to connect wire to the Stryker equipment.
Workers continue to remove old feeder cable in the switchgear room.
Stryker continues to install A/V equipment in the simulation rooms.
AT&T continues telephone feeder installation.
LIBRARY
COMMONS:
The contractor completed work on the custom furniture and display cases.
Facilities Services electricians installed light switches in the multimedia rooms.
MEB
2nd FLOOR LOBBY RENOVATIONS:
The contractor installed sheetrock near the granite columns.
MEB
PHARMACOLOGY LAB RENOVATIONS:
The contractor completed installing light fixtures in the administrative area.
Workers began installing the peninsular casework in Room 5219.
A crew installed black tile around the doorways in the administrative area.
RESIDENCE
HALL LOBBY EXPANSION:
The interior contractor installed sheetrock and taped and floated the fur down in the mezzanine level between the B & C Towers .
The contractor continued framing for the hard ceiling in the expanded lobby area.
ALLIED
HEALTH/NURSING RE-ROOFING:
No work due to rain and high winds.
DENTAL SCHOOL
AUDITORIUMS A & B RENOVATIONS:
The electrical contractor installed additional overhead conduit for the podium, speaker, and projector connections in Auditorium B, extending the conduit into the lobby area.