Louisiana State University Health Sciences Center Administration & Finance
 

Tuesday, April 21, 2009

 

1542 TULANE AVE. :

  • The general contractor continues installing the ceiling grid in Rooms 341, 342 and 343.
    • They continue finishing the new drywall in the 1st Floor lounge.
    • The walls in the auditorium are being primed. 
  • Repairs to the 3rd Floor hallway ceiling grid are underway.
  • The cleaning contractor began cleaning offices along the center hallway on the 3rd Floor.
  • The network wiring contractor completed installing new data drops on the 3rd Floor.
  • The roll-up door contractor completed the punch list items and made final adjustments to the parking garage roll-up door. 
  • Facility Services continued making electrical repairs on the 1st and 3rd Floors.
    • They finished installing new locks and hardware on Rooms 110, 111 and 111A.
    • Crews continued painting the 3rd Floor.

 

EXTERIOR/LANDSCAPING:

  • LSUHSC Facility Services completed installing irrigation piping and sprinklers and began grading the planting beds at the corner of S. Roman St. and Perdido St .

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:    

  • The contractor placed epoxy on the S. Prieur and CSRB sides of the 1st Floor.
    • Crews installed wall and floor tile on the Bolivar St. side of the 1st Floor.
    • They installed restroom tile on the 1st Floor Bolivar St. side of the building.
    • Workers framed and sheet rocked the shaft walls of the new stairwell on the 5th and 6th levels.
    • A crew continued to install granite pavers at the base of the exterior stairwell.
    • Works are insulating the new stairwell. 
  • The electrical contractor ran wire from the controller to the motor for the fire pump.
    • They rewired the tamper proof switches for the fire pump controller and removed the tombstones in the simulation room on the 6th Floor.  

 

LIBRARY COMMONS:

  • The furniture contractor began placing the new furniture.
  • The contractor began removing the restroom partitions. 
  • The contractor continued repairing the custom furniture.
  • LSUHSC Facility Services electricians installed lights in the coffee kiosk.

 

MDL-3 RENOVATIONS:

  • The contractor demolished ceiling grids and tiles, removed light fixtures, and disconnected receptacle outlets. 
  • The A/V contractor de-installed the old LCD and speakers in the main MDL lab area.

 

MEB 2nd FLOOR LOBBY RENOVATIONS:

  • The contractor installed the fur down across from the elevators and removed the loose wire in the open ceiling areas. 
  • The wall panel contractor installed wall panels along the Medical Center Stores wall.

 

MEB PHARMACOLOGY LAB RENOVATIONS:

  • The casework contractor completed touch up work to the casework in the administrative and lab areas. 
  • The plumbing contractor continued installing the sinks in the administrative area. 
  • The contractor applied the final coat of paint in the department head’s office.

 

ALLIED HEALTH/NURSING RE-ROOFING PROJECT:

  • The contractor installed insulation and a cap on a 40-foot section of the roof parallel to Perdido Street . 

 

RESIDENCE HALL LOBBY EXPANSION: 

  • The interior contractor hung ceiling wires in the expanded lobby area. 
  • They prepared the concrete wall to in-set the wall-mounted fire alarm devices.

 

DENTAL SCHOOL AUDITORIUM A & B RENOVATIONS:

  • The electrical contractor installed additional conduit and junction boxes in the crosswalk outside Room 4202.