The general contractor continued finishing drywall in the 1st Floor lounge.
Workers started installing ceiling grid in the 1st Floor lounge.
Crews continue painting the auditorium.
The ceiling grid contractor completed repairs to the 3rd Floor hallway ceiling.
They continued repairing the 2nd Floor front hallway ceiling.
The cleaning contractor continued cleaning offices on the 3rd Floor along the center hallway and began cleaning the front hallway.
Facility Services continued making electrical repairs on the 1st and 3rd Floors and painting rooms on the 2nd and 3rd Floors.
LIONS/LSU
CLINIC PERMANENT REPAIRS AND MITIGATION:
The contractor began installing trim for the windows of the stair tower at the 6th level.
They painted the mechanical room on the 1st Floor, Bolivar Street side.
Workers sealed the original penetrations in the 6th Floor computer lounge.
Crews continued framing and sheet rocking the shaft walls of the stairwell at the 3rd level.
They continued to waterproof the granite wall panels on the new stairwell.
The contractor continued the installation of CMU walls in existing telephone room.
The electrical contractor installed a junction box for the new fiber cables on the 6th Floor, Bolivar Street side.
They continued wiring the firemans switch for the exhaust fans in the new stairwell and installed the door closure on the 6th Floor Gravier Street side.
Stryker is installing microphones in the large lecture room on the 6th Floor.
LIBRARY
COMMONS:
LSUHSC electricians relocated light fixtures above the magazine racks.
MDL-3
RENOVATIONS:
The contractor completed demolition in the MDL.
The abatement contractor began preparation for abatement over the weekend.
RESIDENCE
HALL LOBBY EXPANSION:
The contractor installed ceiling grid for the sheetrock ceiling underneath the mezzanine level of the A & B Towers and in the expanded lobby area.
They installed ceiling grid for the acoustical ceiling between the B & C Towers .
MEB
2nd FLOOR LOBBY RENOVATIONS:
The contractor began installing new metal around the elevators.
The wall panel contractor finished installing wall panels along the Medical Center Stores wall.
MEB
PHARMACOLOGY LAB RENOVATIONS:
The contractor continued installing receptacle raceways in the laboratory area.
The contractor continued connecting drains to the sinks and installed plumbing fixtures in the laboratory area.
ALLIED
HEALTH/NURSING RE-ROOFING PROJECT:
The contractor continued installing insulation and a cap on S. Roman street side of the roof.There are eight feet remaining.
DENTAL SCHOOL
AUDITORIUMS A & B RENOVATIONS:
The electrical contractor completed installing additional conduit and junction boxes in the crosswalk outside Room 4202.