Louisiana State University Health Sciences Center Administration & Finance
 

MONDAY, APRIL 6, 2009

 

1542 TULANE AVE. :

  • The general contractor continued finishing the new drywall in Rooms 341, 342, and 343.
    • Workers continued painting the walls and began the installation of the ceiling grid in the 2nd Floor lounge.
  • The mechanical contractor started installing plumbing in the 1st Floor lounge.
  • The electrical contractor continued wiring fan coil units on the 3rd Floor.
  • The roll-up door contractor completed installation of the new parking garage roll-up door.
    • They continued wiring the controller.
  • Facility Services continued painting and making electrical repairs on the 2nd and 3rd Floors.

 

EXTERIOR/LANDSCAPING:

  • Facility Services continued planting shrubs in the rear of the Resource Center along S. Prieur St .

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:   

  • The contractor grouted floor tile in the computer lounge.
  • Crews installed granite on the front edge of the sidewalk around the stair tower.
  • Workers painted on the 1st Floor near the freight elevator and installed the stair door on the 1st Floor near the passenger elevator.
  • The contractor installed the 2nd coat of waterproofing in the freight elevator pit.

 

LIBRARY COMMONS:

  • The contractor installed wall covering in the large multimedia room.
  • The contractor corrected minor deficiencies in the display cases.  
  • LSUHSC Facility Services electricians installed egg lights.

 

MEB 2nd FLOOR LOBBY RENOVATIONS:

  • The contractor framed the soffit across from the elevator. 

 

MEB PHARMACOLOGY LAB RENOVATIONS:

  • The casework contractor continued installing the peninsular casework in Room 5219 and placed the two remaining fume hoods.
  • The contractor installed the final door frame in the administrative area.
  • The mechanical contractor started connecting the fume hoods. 

 

RESIDENCE HALL LOBBY EXPANSION: 

  • The interior contractor continued installing sheetrock and taped and floated the fur down in the mezzanine level between the B & C Towers .
  • The contractor relocated fire sprinkler heads between A and B Tower.

 

ALLIED HEALTH/NURSING RE-ROOFING:

  • The contractor removed another 30 ft section of the roof parallel to Bolivar Street and applied the two-ply temporary roof. 
  • The contractor is now past the elevator penthouse. 

 

DENTAL SCHOOL AUDITORIUMS A & B RENOVATIONS:

  • The electrical contractor installed multimedia conduit in the lobby.