Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, APRIL 8, 2009

 

1542 TULANE AVE. :

  • The general contractor continues finishing the drywall in Rooms 341, 342 and 343.
    • The walls in the 2nd Floor lounge are being painted.
    • Workers completed the ceiling grid installation and began installing ceiling tiles in the 2nd Floor lounge.
  • The mechanical contractor is roughing in the plumbing in the 1st Floor lounge.
    • Workers installed drain lines on the new fan coil units in Rooms 345, 343 and 342.
  • The network wiring contractor continues installing new drops in the 3rd Floor offices.
  • The roll-up door contractor is adjusting the controller for the new garage roll-up door.
  • Facility Services continues painting and making electrical repairs on the 2nd and 3rd Floors.

 

EXTERIOR/LANDSCAPING:

  • Facility Services completed installing all piping and sprinklers for station # 11 on the S. Roman St. side of the MEB.

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:

  • The contractor installed wall covering in the 6th Floor computer lounge.
    • Crews installed break metal interior trim for the windows of the new stairwell on the 1st level.
    • Workers continue installing new countertops in the computer lounge and installing cove base on the Gravier St. side of the 6th Floor.
    • The granite cap is being installed at the top of the new stairwell.
  • The electrical contractor installed lights and receptacles on the S. Prieur St. side of the 1st Floor.
    • They installed wire for the sump pump for the elevator on the 1st Floor, Bolivar Street side.
    • Crews installed stairwell lights on the 1st level.
  • Stryker installed speakers in the large lecture room and installed routers in the network closet on the 6th Floor.
  • AT&T continued to install wires in the new room on the 2nd Floor to allow for the transfer of the phone lines from the 1st to the 2nd Floor.

 

LIBRARY COMMONS:

  • The contractor installed wall covering along the window wall.
  • The fire alarm devices are being installed.  
  • LSUHSC Facility Services electricians installed new exit signs.

 

MEB 2nd FLOOR LOBBY RENOVATIONS:

  • The contractor re-installed the window frames for the store fronts. 

 

MEB PHARMACOLOGY LAB RENOVATIONS:

  • The casework contractor continued installing casework in Rooms 5219, 5219A and 5262. 
  • Door frames were installed in the lab area.
  • The contractor installed vinyl wall covering for the animal care room.

 

RESIDENCE HALL LOBBY EXPANSION: 

  • The interior contractor continued installing sheetrock on the fur down in the expanded lobby area.
    • They are taping and floating the new sheetrock as it is hung. 

 

ALLIED HEALTH/NURSING RE-ROOFING:

  • The contractor removed a 30-foot roof section of the old roof parallel to Roman St. at the MEB side of the elevator penthouse and applied the two-ply temporary roof. 

 

DENTAL SCHOOL AUDITORIUMS A & B RENOVATIONS:

  • The electrical contractor installed Unistrut in the elevator lobby for the additional overhead conduit.