The general contractor continues finishing the drywall in Rooms 341, 342 and 343.
The walls in the 2nd Floor lounge are being painted.
Workers completed the ceiling grid installation and began installing ceiling tiles in the 2nd Floor lounge.
The mechanical contractor is roughing in the plumbing in the 1st Floor lounge.
Workers installed drain lines on the new fan coil units in Rooms 345, 343 and 342.
The network wiring contractor continues installing new drops in the 3rd Floor offices.
The roll-up door contractor is adjusting the controller for the new garage roll-up door.
Facility Services continues painting and making electrical repairs on the 2nd and 3rd Floors.
EXTERIOR/LANDSCAPING:
Facility Services completed installing all piping and sprinklers for station # 11 on the S. Roman St. side of the MEB.
LIONS/LSU
CLINIC PERMANENT REPAIRS AND MITIGATION:
The contractor installed wall covering in the 6th Floor computer lounge.
Crews installed break metal interior trim for the windows of the new stairwell on the 1st level.
Workers continue installing new countertops in the computer lounge and installing cove base on the Gravier St. side of the 6th Floor.
The granite cap is being installed at the top of the new stairwell.
The electrical contractor installed lights and receptacles on the S. Prieur St. side of the 1st Floor.
They installed wire for the sump pump for the elevator on the 1st Floor, Bolivar Street side.
Crews installed stairwell lights on the 1st level.
Stryker installed speakers in the large lecture room and installed routers in the network closet on the 6th Floor.
AT&T continued to install wires in the new room on the 2nd Floor to allow for the transfer of the phone lines from the 1st to the 2nd Floor.
LIBRARY
COMMONS:
The contractor installed wall covering along the window wall.
The fire alarm devices are being installed.
LSUHSC Facility Services electricians installed new exit signs.
MEB
2nd FLOOR LOBBY RENOVATIONS:
The contractor re-installed the window frames for the store fronts.
MEB
PHARMACOLOGY LAB RENOVATIONS:
The casework contractor continued installing casework in Rooms 5219, 5219A and 5262.
Door frames were installed in the lab area.
The contractor installed vinyl wall covering for the animal care room.
RESIDENCE
HALL LOBBY EXPANSION:
The interior contractor continued installing sheetrock on the fur down in the expanded lobby area.
They are taping and floating the new sheetrock as it is hung.
ALLIED
HEALTH/NURSING RE-ROOFING:
The contractor removed a 30-foot roof section of the old roof parallel to Roman St. at the MEB side of the elevator penthouse and applied the two-ply temporary roof.
DENTAL SCHOOL
AUDITORIUMS A & B RENOVATIONS:
The electrical contractor installed Unistrut in the elevator lobby for the additional overhead conduit.