Louisiana State University Health Sciences Center Administration & Finance
 

THURSDAY, APRIL 9, 2009

 

1542 TULANE AVE. :

  • The general contractor continued to tape and float the new drywall in Rooms 341, 342 and 343.
    • Workers are painting the walls, installing ceiling tiles and installing light fixtures in the 2nd Floor lounge.
  • The access control contractor began installing door contacts on the emergency exit doors on the Charity side of the 1st Floor hallway.
  • The flooring contractor installed carpet in offices on the 2nd and 3rd Floors.
  • The mechanical contractor continued installing plumbing in the 1st Floor lounge.
    • They finished installing drain lines for the new fan coil units in Rooms 345, 343 and 342.
  • The network wiring contractor continues installing new network drops in the 3rd Floor offices.
  • The roll-up door contractor completed adjusting the controller for the new garage door.
  • Facility Services continued painting and electrical repairs on the 2nd and 3rd Floors.

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:

  • The contractor began refurbishing the existing window frames on CSRB side of the 6th Floor.
    • They installed additional ceiling grid on the Gravier St. side of the 6th Floor.
    • Workers continued installing the granite cap at the top of the exterior stairwell.
  • The electrical contractor installed ceiling lights on the 6th Floor and stairwell lights on the 1st and 2nd Floors.
  • Stryker tested the medical equipment system.
  • AT&T continued to install wires in the new room on the 2nd Floor to allow for the transfer of the phone lines from the 1st to the 2nd Floor.

 

LIBRARY COMMONS:

  • The contractor installed wall covering in the restrooms.

 

MEB 2nd FLOOR LOBBY RENOVATIONS:

  • The contractor continued to build the soffit across from the elevators. 

 

MEB PHARMACOLOGY LAB RENOVATIONS:

  • The casework contractor installed countertops in Rooms 5219, 5219A and 5262. 
  • The contractor heat welded the vinyl wall covering for the animal care room.

 

RESIDENCE HALL LOBBY EXPANSION:

  • The interior contractor continued to tape and float the fur down in the expanded lobby area. 
  • The mechanical contractor raised the sprinkler pipes in the expanded lobby area.

  

    DENTAL SCHOOL AUDITORIUMS A & B RENOVATIONS:

  • The electrical installed conduit in the lobby for the multimedia equipment. 
  • The contractor framed the raised stage area underneath Auditorium C (for the IT closet).