Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, MAY 19, 2009

 

1542 TULANE AVE. :

  • The contractor installed a door frame in the 1st Floor lobby. 
  • Facility Services continued working on 4th Floor fan coils (Room 441) and continued electrical repairs on the 1st Floor.

 

EXTERIOR/LANDSCAPING:

  • Facility Services planted shrubs at the corner of Perdido St. and S. Roman St .

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:    

  • The mechanical contractor continued installing the 1st Floor, Bolivar St. restroom lavatory fixtures. 
  • The contractor aligned the entrance doors on the Gravier Street side.
    • Workers replaced damaged tiles in the restrooms on the Bolivar St. side on the 6th Floor.
    • Crews built knee walls on the 2nd level of the new exterior stairwell.
    • They continued installing wall tile on the 1st Floor, Bolivar Street side.
  • The electrical contractor pulled and terminated wire to the switchgear.
    • They installed an outlet in the old PBX room and lights in the 1st level of the stairwell.
  • The telephone contractor strapped down the splice case on the 1st Floor in the old PBX room.

 

RESIDENCE HALL LOBBY EXPANSION:

  • The flooring contractor continued installing tiles toward the Perdido St. side.

 

MEB AIR HANDLING UNIT REPLACEMENT:

  • The contractor completed insulating piping on roof top unit #2 (RTU #2).

 

MEB MDL 3 RENOVATIONS:

  • The contractor continued installing steel track for the new partition in Room 4108A.
  • They are installing framing studs around the steel track for sound insulation. 
  • Workers stubbed up plumbing for the new casework.

 

MEB 2nd FLOOR LOBBY RENOVATIONS:

  • The contractor continues installing wooden panels near the Womens restroom.

 

MEB PHARMACOLOGY LAB RENOVATIONS:

  • The network wiring contractor continued pulling network wires in the lab area. 
  • The contractor continued to install wire molding and exit lights. 
  • A crew started installing the exhaust ductwork.

 

ALLLIED HEALTH/NURSING RE-ROOFING PROJECT:

  • The contractor continued replacing the parapet wall cap along Gravier Street .   

     

DENTAL SCHOOL AUDITORIUMS A & B RENOVATIONS:

  • The contractor pulled wires for the dimmer control boxes in Auditorium B and installed the dimmer panel for Auditorium A.  
  • The door frames have been painted.  
  • The A/V contractor pulled wires in the 4th Floor walkway.