Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, JUNE 2, 2009

 

1542 TULANE AVE. :

  • The contractor fabricated the wood forms for the installation of bollard lights along Tulane Ave.  
  • The contractor continued working on punch-list items; capping plumbing lines on Floors 2, 3, 4, and 5 in the rear section of the building.
  • The insulation contractor insulated fan coil pipes on the 2nd and 3rd Floors.
  • Facility Services continues to install and connect fan coils in offices on Floors 2, 3, and 4.

 

EXTERIOR/LANDSCAPING:

  • Facility Services installed sod in front of the Allied Health/Nursing Building.

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:    

  • The contractor removed the old generator and switchgear from the building and placed the new fuel tank.

 

LIONS BUILDING 8th FLOOR NETWORK CLOSET:

  • The contractor continued framing and installing sheetrock.

 

LIBRARY COMMONS:

  • The contractor continued framing and installing sheetrock for the center stairwell wall.
  • Carpet was installed in the back office area.

 

RESIDENCE HALL 2ND FLOOR LOBBY EXPANSION:

  • The contractor removed a portion of a wall and a door near the A Tower lobby area to create an encased opening corner near Roman St. and the parking lot.

 

MEB AIR HANDLING UNIT REPLACEMENT:

  • Facility Services continues to monitor and make adjustments to the temporary air conditioning units for the 6th and 7th Floor Quadrant D.
  • The contractor continued installing duct work for AHU 6D and 7D.

 

MEB 2nd FLOOR LOBBY RENOVATIONS:

  • The contractor began installing metal wall panels near Lecture Hall B.

 

MEB MDL #3 RENOVATIONS:

  • The contractor continued installing sheetrock for the alcove area across from MDL #5.

 

MEB PHARMACOLOGY LAB RENOVATIONS:

  • The contractor continued installing the cubicles in the administrative area. 
  • The contractor patched the terrazzo floor. 

 

  DENTAL SCHOOL AUDITORIUMS A & B RENOVATIONS:

  • The electrical contractor installed wiring for fire alarm devices in the 4th Floor elevator lobby and the 4th Floor walkway. 
  • Fire alarm devices were installed in Auditorium A. 
  • The contractor installed additional framing for the acoustical wall panels along the rear and side walls in Auditorium B. 
  • The A/V contractor installed fans and auxiliary outlets for their equipment racks in Room 4202B.

 

DENTAL SCHOOL PARKING LOT AND ROAD REPAIRS:

  • The contractor continued making repairs to Parking Lots 2 and 6.
  • Work has started on the repairs to the Moss Street entrance driveway.