The contractor connected the sink and ice machine for the 2nd Floor lounge and worked on AHU-C in Suite 235 .
Facility Services is applying touch-up paint in 2nd Floor offices.
Facility Services continues to install and connect fan coils in offices on the 2nd Floor.
EXTERIOR/LANDSCAPING:
Facility Services continues spot patching sod at various areas on the downtown campus and continued irrigation piping along Bolivar St. alongside the Residence Hall.
LIONS/LSU
CLINIC PERMANENT REPAIRS AND MITIGATION:
The electrical contractor removed underground wires from the old generator room and fire pump room and tested the 660 gallon fuel tank on the 1st Floor.
LIONS BUILDING
8th FLOOR NETWORK CLOSET:
The contractor painted the interior of the network closet.
RESIDENCE
HALL 2ND FLOOR LOBBY EXPANSION:
The interior contractor installed fire alarm devices in the lobby area between the B & C Towers .
The contractor installed ceiling tiles in the back corner lobby area of the A Tower.
Crews continued taping and floating the gypsum board ceiling in the expanded lobby area.
ALLIED
HEALTH/NURSING BLDG RE-ROOFING PROJECT:
The contractor removed and began replacing the 4th Floor roof along Gravier Street .
MEB
AIR HANDLING UNIT REPLACEMENT:
Facility Services continues to monitor and make adjustments to the temporary air conditioning units for the 6th and 7th floors Quadrant D.
The contractor continued connecting building automation controls for AHU 6D.
They completed insulating the heating hot water piping and continued connecting building automation controls for AHU 7D.
MEB
2nd FLOOR LOBBY RENOVATIONS:
The contractor installed wall panels on the right side of Lecture Hall A.
MEB
MDL #3 RENOVATIONS:
The contractor prepped the floor for VCT installation.
Workers installed ceiling grids in Rooms 4108A and 4201A.
MEB
PHARMACOLOGY LAB RENOVATIONS:
The contractor began waxing the floors in the lab section.
DENTAL SCHOOL
AUDITORIUMS A & B RENOVATIONS:
The contractor installed acoustical panels on the east wall and framing along the south wall of Auditorium B.
The AV contractor installed components in the A/V racks in Room 4202B.
The electrical contractor installed wall-mounted lights along the walls of Auditorium B.
The mechanical contractor set the 2nd Liebert unit and began connecting the chilled water piping.
DENTAL SCHOOL
PARKING LOT AND ROAD REPAIRS:
The contractor completed the concrete driveway apron repairs, with the exception of the Navy Parkway exit drive.