Facility Services is applying touch-up paint in the 1st Floor offices.
Facility Services custodial staff vacuumed additional rooms along the center corridor on the 2nd Floor.
EXTERIOR/LANDSCAPING:
Facility Services continues to install the sprinkler system on the Tulane Ave. side of the Roman St. Garage.
ALLIED
HEALTH/NURSING RE-ROOFING PROJECT:
The contractor installed lighting protection rods on the Stairwell C penthouse.
Workers continued installing flashing around the exhaust fans.
LIONS/LSU
CLINIC PERMANENT REPAIRS AND MITIGATION:
The contractor continued pulling network cables for the conference rooms on the CSRB side of the 6th Floor.
LIBRARY
COMMONS:
The contractor continued installing the handrail in the stairwell.
RESIDENCE
HALL 2nd FLOOR LOBBY EXPANSION:
The contractor removed the existing corner guards.
Workers continued taping and floating walls throughout the lobby.
The flooring contractor continued installing porcelain bases between the A & B Towers .
MEB
AIR HANDLING UNIT REPLACEMENT:
Facility Services continues shifting temporary AC units from the C Quadrant on the 6th and 7th floor to the B Quadrant (corner of Perdido Street and South Roman Street ).
The contractor continues installing piping, insulation, electrical and controls for AHU 6C.
MEB
MDL #3 RENOVATIONS:
The network contractor continued running network wires for the casework.
DENTAL SCHOOL
AUDITORIUMS A & B RENOVATIONS:
The A/V contractor installed the auto-stack camera for the projectors in Auditorium A.
The general contractor continued pulling wires and touched up paint in Auditorium A.
The electrical installed electrical outlets for the podiums.