Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, JULY 15, 2009

 

1542 TULANE AVE. :

  • Facility Services is applying touch-up paint in the 2nd Floor offices along Tulane Ave.
  • The network contractor installed wireless services in the lounge and conference room on the 2nd Floor. 
  • The lighting contractor installed additional lighting in various locations on the 1st and 2nd Floors. 

 

EXTERIOR/LANDSCAPING:

  • Facility Services continued installing sprinklers on the Tulane Avenue side of the Roman Street Garage. 

 

ALLIED HEALTH/NURSING BLDG RE-ROOFING PROJECT: 

  • The contractor continued installing aluminum flashing around the parapet wall on the Atrium along the Bolivar Street Side. 
  • The contractor completed the installation of the lightning protection system. 

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:

  • The contractor installed the flood gate on the freight elevators.
  • The fire sprinklers were installed in the old switch gear room on the 1st Floor.
  • Workers installed the supports for the MRI trailer hook up and pulled data wire on the CSRB side of the 6th Floor.

 

RESIDENCE HALL 2nd FLOOR LOBBY RENOVATIONS:  

  • The millwork contractor continued installing wood cladding around the mailboxes.
  • The interior contractor continued patching walls throughout the lobby.
  • The floor contractor installed porcelain bases in the corner lobby area of the A & C towers.

 

MEB AIR HANDLING UNIT REPLACEMENT:

  • Facility Services continued monitoring and adjusting temporary AC units for the B Quadrant (corner of Perdido Street and South Roman Street ).
  • The contractor continued installing new ductwork and piping for air handling unit 6-B and began installing ductwork for air handling unit 7-B.

 

MEB 2nd FLOOR LOBBY RENOVATIONS:

  • The contractor continued to repair the interior of the Campus Stores space.

 

MEB MDL #3 RENOVATIONS:

  • The contractor taped and floated wall leading to Room 4210.

 

MEB 7th FLOOR PHYSIOLOGY LAB RENOVATIONS:

  • The contractor continued removing existing casework, ceiling grids and tiles, light, and HVAC duct from Rooms 7221, 7241, 7244, and 7250.

 

DENTAL SCHOOL AUDITORIUMS A & B RENOVATIONS:

  • The A/V contractor continued to install equipment in room 4202B and both auditoriums.
  • The contractor installed network terminals in Auditorium A.