Louisiana State University Health Sciences Center Administration & Finance
 

MONDAY, JULY 27, 2009

 

1542 TULANE AVE. :

  • Facility Services continued applying touch-up paint in the 1st floor offices along Tulane Ave and painted the doors and frames leading into the auditorium.
  • Facility Services completed electrical repairs in Room 235K. 
  • The contractor installed CMU for the pipe chase on the 1st and 2nd Floors of the parking garage.
  • The contractor installed sheetrock above the 1x1 ceiling in the student lounge area.

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:

  • The contractor finished pulling wires to the temporary MRI trailer disconnect switch and transformer. 

 

RESIDENCE HALL 2nd FLOOR LOBBY RENOVATIONS:  

  • The contractor continued priming the stairwell doors and frames.

 

ALLIED HEALTH/NURSING BLDG ROOF REPLACEMENT:

  • The contractor continued installing aluminum flashing around the 4th Floor ledge near Gravier Street .

 

MEB AIR HANDLING UNIT REPLACEMENT:

  • Facility Services began transferring temporary AC units from the B to the A Quadrant (corner of South Roman Street and the MEB loading dock).
  • The contractor continued installing and insulating new hot water piping, testing and balancing air handling unit 6-B and 7-B.

 

MEB 2nd FLOOR LOBBY RENOVATIONS:

  • The contractor finished installing carpet in Medical Center Stores.
  • Crews leveled the floor in preparation of the carpet in Campus Office Stores.
  • They caulked around the thresholds for both stores.

 

MEB 7th FLOOR PHYSIOLOGY LABS RENOVATIONS:

  • The contractor continued patching walls in Room 7241 and 7250.

 

DENTAL SCHOOL AUDITORIUMS A & B RENOVATIONS:

  • The contractor tested the network cables in Auditorium B.
  • The A/V contractor programmed the podium equipment in Auditorium A.