The coffee kiosk for the 1st Floor lounge was delivered.
Facility Services continues applying touch-up paint in the 1st Floor offices along Tulane Ave.
The contractor completed installation of CMU for the pipe chase on the 1st and 2nd Floors.
The network wiring contractor installed data runs in Rooms 228 and 240A.
LIONS/LSU
CLINIC PERMANENT REPAIRS AND MITIGATION:
The contractor provided emergency power to the fire pump room.
RESIDENCE
HALL 2nd FLOOR LOBBY RENOVATIONS:
The contractor continued priming the stairwell door frames and elevator door frames.
The flooring contractor installed porcelain bases in back corner lobby area of the A & C Towers .
ALLIED
HEALTH/NURSING BLDG. ROOF REPLACEMENT:
The contractor continued installing aluminum flashing around the 4th Floor ledge near Gravier Street .
MEB
AIR HANDLING UNIT REPLACEMENT:
Facility Services is transferring the temporary AC units from the B to the A Quadrant (corner of South Roman Street and the MEB loading dock) in preparation for the installation of the next pair of new air handling units.
The contractor continued installing and insulating new hot water piping for AHUs 6-B and 7B.
They are testing and balancing the two new units.
MEB
2nd FLOOR LOBBY RENOVATIONS:
The contractor caulked all of the door frames.
The furniture contractor completed furniture installation.
MEB
4th FLOOR MDL #3 RENOVATIONS:
The contractor installed door for the partition Storage Room 4210A.
MEB
7th FLOOR PHYSIOLOGY LAB RENOVATIONS:
The contractor installed wood blocking in Room 7244 and removed sheetrock in Rooms 7221, 7241, & 7250.
The contractor began taping and floating the sheetrock repairs.
DENTAL SCHOOL
AUDITORIUMS A & B RENOVATIONS:
The contractor continued testing network wires in Auditorium B and completed punch list items in Auditorium B.
A/V contractor conducted heat tests for the projectors in Auditorium A.