The contractor painted the rear wall of the 1st Floor coffee kiosk station.
The contractor installed the counter top and the electrical subpanel for the kiosk.
The contractor replaced broken windows on the 3rd Floor.
DENTAL SCHOOL
AUDITORIUMS A & B RENOVATIONS:
The demonstration of the new multi-media system installed in the auditoriums was successful.
MEB
AIR HANDLING UNIT REPLACEMENT:
Facility Services continued monitoring and adjusting the temporary A/C units in the A Quadrant (corner of South Roman Street and the MEB loading dock).
The insulation of the chilled and heating hot water piping at AHU 6A is complete.
The control wiring for AHU 6A is finished.
The fire alarm wiring for AHU 7A is complete.
LANDSCAPING:
Workers continued with the planting along the Tulane Ave. side of the Roman St. Garage.
MEB
2nd FLOOR LOBBY RENOVATIONS:
The contractor installed the hidden doors.
MEB
7TH FLOOR PHYSIOLOGY LABS RENOVATIONS:
The contractor painted the 1st finish coat in Rooms 7221, 7241, 7244, and 7250.
The contractor roughed in the gas line in Room 7244.
RESIDENCE
HALL 2nd FLOOR LOBBY RENOVATIONS:
The furniture contractor began installing the security desk station in the expanded lobby area.
The contractor relocated the exit sign and pull station to the new wall by the telephone panel.