Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, AUGUST 19, 2009

 

1542 TULANE AVE. :

  • The contractor placed the equipment for the 1st Floor coffee kiosk.
  • The painter painted the walls in the 1st Floor lounge.

 

DENTAL SCHOOL AUDITORIUM A & B RENOVATIONS:

  • The A/V contractor configured connections from the A/V rack to the Access Grid rack.
  • IT configured additional components of the Access Grid in the A/V Room.

 

EXTERIOR/LANDSCAPING:

  • Facility Services commenced installing irrigation piping on the Gravier Street side of the Roman Garage. 

 

MEB AIR HANDLING UNIT REPLACEMENT:

  • Facility Services continued relocating the temporary A/C units to the 4th and 5th Floor Quadrant D (corner of Bolivar Street and Perdido Street ).
  • The contractor continued testing and balancing air handling units 6-A and 7-A.

 

MEB 2nd FLOOR LOBBY RENOVATIONS:

  • The wall panel contractor installed the second set of the metal wall panels.   

 

MEB 7th FLOOR PHYSIOLOGY LABS RENOVATIONS:

  • The contractor roughed in the electrical for Rooms 7241, 7244, and 7250.   

 

RESIDENCE HALL 2nd FLOOR LOBBY RENOVATIONS:  

  • The contractor continued installing metal screen on the security desk.