TUESDAY, SEPTEMBER 1, 2009NOTICE: The Medical Education Building Air Handling Unit Replacement project continues with the ongoing replacement of the two air handling units that serve the Perdido Street/Bolivar Street corner of the 4th and 5th Floors. The next two air handling units to be replaced serve the Bolivar Street/MEB Loading Dock corner (Quadrant C) of the 4th and 5th Floors. Installation of these units will start at 6:00 PM on Friday, September 11, 2009.
Facility Services needs to remove and relocate the temporary power breakers for the temporary air conditioning units that were set up for the Roman Street/MEB Loading Dock corner (Quadrant A). Consequently, there will be an electrical outage on Thursday, September 3rd from 6:00 AM to 7:00 AM to remove the temporary breakers. During this outage there will be no power to equipment plugged into receptacles in labs and offices that are served out of main panels DL6A and DL7A which affects panels LA6A, LA6B, LA6C, LA6D, LA6E, LA6F, LA7A, LA7B, LA7C, LA7D, LA7E and LA7F. Receptacles are labeled in the labs, identifying the panel that supplies the power to the receptacle. On Friday, September 4th there will be an electrical outage from 5:00 AM to 7:00 AM to install temporary breakers to serve the power panels for the temporary air conditioning units in the Bolivar Street/MEB Loading Dock corner (Quadrant C). During this outage there will be no power to equipment plugged into receptacles in labs and offices that are served out of main panels DL5C which affects panels LC5A, LC5B, LC5C, LC5D, LC5E and LC5F. Receptacles are labeled in the labs, identifying the panel that supplies the power to the receptacle. 1542 TULANE AVE. :
DENTAL SCHOOL AUDITORIUM A & B RENOVATIONS:
EXTERIOR/LANDSCAPING:
MEB AIR HANDLING UNIT REPLACEMENT:
MEB 7th FLOOR PHYSIOLOGY LABS RENOVATION:
RESIDENCE HALL 2nd FLOOR LOBBY EXPANSION:
RESOURCE CENTER ROOF REPLACEMENT:
|
| Disclaimer | © 2013 LSUHSC | Privacy Policy |