The contractor framed the walls in Rooms 203 and 242B.
Workers created a rough opening between Rooms 202A and 203.
The mechanical contractor installed isolation valves on the heating and chilled water lines and removed the existing fan coil unit and piping in Room 203.
DENTAL SCHOOL
AUDITORIUM A & B RENOVATIONS:
The contractor roughed in for the access control components.
EXTERIOR/LANDSCAPING:
Facility Services installed irrigation piping around the T-lot.
MEB
AIR HANDLING UNIT REPLACEMENT:
Facility Services continued monitoring the temporary A/C units in the 4th and 5th Floor Quadrant C (corner of Bolivar Street and MEB loading dock).
The contractor insulated piping for AHU 4-C.
They continued installing electrical and control wiring for AHU 4-C and 5-C.
AHU parts for 4-A, 4-B, 5-A and 5-B were moved to the T-lot for temporary storage.
MEB
7th FLOOR PHYSIOLOGY LABS RENOVATION:
The contractor continued installing the new lab countertops in Room 7244.
Crews continued installing electrical raceway and receptacle outlet for the center islands in Rooms 7221, 7241, and 7250.
MEB
MORGUE AUTOPSY HVAC UPGRADE:
The contractor removed the existing exhaust duct on the 1st Floor.