Louisiana State University Health Sciences Center Administration & Finance
 

THURSDAY, SEPTEMBER 3, 2009

 

1542 TULANE AVE. :

  • The contractor erected a temporary wall at the 1st floor garage/building entrance.
  • The contractor removed the remediation containment barriers for the 2nd Floor Garage corridor build-out.
  • The contractor touched-up the paint on the walls and door frames in the coffee kiosk area.    

 

ALLIED HEALTH/NURSING BLDG. REROOFING PROJECT:

  • The contractor continued to repair the metal panels of the atrium roof.

 

DENTAL SCHOOL AUDITORIUM A & B RENOVATIONS:

  • The A/V contractor labeled and tested the A/V communication cables in Room 4202B that communicate with components in Auditorium B.
  • The network wiring crew tested network wires for the wireless access connections in Auditoriums A and B.

 

EXTERIOR/LANDSCAPING:

  • Facility Services planted shrubs beside the Central Plant along Gravier Street and continued demolition of asphalt around the perimeter of the T-lot.

 

MEB AIR HANDLING UNIT REPLACEMENT:

  • Facility Services monitored and adjusted the temporary A/C units to the 4th and 5th Floor Quadrant D (corner of Bolivar Street and Perdido Street ).
  • The contractor commenced testing and balancing of air handling units 4-D and 5-D. 

 

MEB 7th FLOOR PHYSIOLOGY LABS RENOVATION:

  • The contractor completed installing light fixtures in Rooms 7221 and 7244.
  • The contractor continued installing lab furniture in Rooms 7241 and 7250.
  • The contractor installed HVAC supply grilles in Room 7241.

 

RESOURCE CENTER ROOF REPLACEMENT:

  • The contractor lowered seven roof drains and applied the two-ply temporary roof system on the Gravier Street side of the building.
    • They have now completed 24 of 34 roof drains.