Louisiana State University Health Sciences Center Administration & Finance
 

FRIDAY, OCTOBER 2, 2009

 

1542 TULANE GARAGE ENTRANCES:

  • The contractor placed the concrete curbs and filled the slab penetrations at the 1st Floor handicap entrance. 
  • The contractor pulled wiring for the power receptacles at the 2nd level garage corridor.

 

EXTERIOR/LANDSCAPING:

  • Facility Services continued installing irrigation piping adjacent to the Roman St. Garage along Bolivar Street .

 

LIONS/LSU CLINIC BLDG. 8TH FLOOR RENOVATIONS:

  • Facilities Services continued with the demolition of the conference and lobby areas.

 

MEB AIR HANDLING UNIT REPLACEMENT:

  • Facility Services continued monitoring temporary A/C units in the 4th and 5th Floor Quadrant B (corner of South Roman Street and Perdido Street ).
  • The contractor started the demolition of AHU 4-B and 5-B and removed the louvers on both mechanical rooms. 

 

MEB 4TH FLOOR MDL #4 RENOVATIONS:

  • The contractor removed the old speakers and projector screens.

 

RESIDENCE HALL LOBBY RENOVATIONS:

  • The contractor installed four exit signs and replaced light bulbs.