The contractor sanded and primed the sheetrock walls at the 2nd level garage entrance.
They installed the automatic door at the 1st Floor garage entrance.
CITY
PARK CAMPUS:
The fencing contractor completed the installation of top rails, bottom rails, and tension bars along Florida Ave.
The contractor started driving piles along Florida and Moss Ave.
EXTERIOR/LANDSCAPING:
Facility Services installed irrigation piping adjacent to the Roman Garage along S. Roman Street .
LIONS/LSU
CLINIC BLDG. 8TH FLOOR RENOVATIONS:
Facilities Services continued roughing in the plumbing for the small coffee room.
RESOURCE
CENTER LIBRARY COMMONS:
The contractor fixed the floor tile and carpet at the main entrance.
MEB
2nd FLOOR LOBBY RENOVATIONS:
The contractor completed installing the metal wall panels.
MEB
AIR HANDLING UNIT REPLACEMENT:
Facility Services continued relocating and installing temporary A/C units in the 4th and 5th Floors A Quadrant (corner of South Roman Street and the MEB loading dock).
The contractor continued balancing and testing AHUs 4-B and 5-B.
MEB
4TH FLOOR MDL #4 RENOVATIONS:
The contractor continued roughing in for the new plumbing and electrical.
The contractor installed sheetrock in Room 4210.
The contractor installed corner guards along the corridor.
RESIDENCE
HALL 2ND FLOOR LOBBY RENOVATIONS:
The State Fire Marshal completed his inspection and granted approval for occupancy.
The contractor continued installing the precast concrete bench.
RESOURCE CENTER ROOFING PROJECT:
The contractor started the installation of the first ply of the 2-ply roofing system on the Gravier St. penthouse and in the corner of Gravier and South Prieur Streets.
UPTOWN
CAMPUS:
The contractor continued the testing and programming of the new chillers.