The contractor taped and floated the walls in Room 242 for the 2nd level garage corridor.
EXTERIOR/LANDSCAPING:
Facility Services continued installing irrigation piping adjacent to the Roman St. Garage along Bolivar Street and began the final grading around the T-lot.
LIONS/LSU
CLINIC BLDG. 8TH FLOOR RENOVATIONS:
Facilities Services continued the demolition of the conference and lobby areas.
The general contractor hung sheetrock in Room 804 (lab area that is being converted into the conference room).
MEB
AIR HANDLING UNIT REPLACEMENT:
Facility Services continued monitoring temporary A/C units in the 4th and 5th Floor Quadrant B (corner of South Roman Street and Perdido Street ).
The contractor completed installing chilled water piping for AHU 4-B and 5-B.
They continued installing ductwork for both of the new air handling units.
Crews balanced RTU 1, RTU 2, and all AHUs on the 6th and 7th Floors.
MEB
4TH FLOOR MDL #4 RENOVATIONS:
The contractor removed the old floor tile.
MEB
7th FLOOR PHYSIOLOGY LABS RENOVATIONS:
The contractor buffed and waxed the floors in all 4 rooms
RESIDENCE
HALL LOBBY RENOVATIONS:
The contractor continued placing and setting the precast stone on the concrete wall.
RESOURCE CENTER ROOFING PROJECT:
The contractor prepped the roof deck for the lightweight concrete on the corner of Gravier St. and S. Prieur St .).
UPTOWN
CAMPUS CHILLER REPLACEMENT:
The Uptown Campus is the former site of the New Orleans Adolescent Hospital .
The contractor installed the condenser water pumps and completed the exterior condenser piping.
The contractor removed the existing chilled water pumps.