FRIDAY, OCTOBER 9, 2009

 

1542 TULANE AVE. :

  • The contractor painted walls in Room 242B.
  • Workers floated the sheetrock in Room 202A for the 2nd level garage corridor and at the S. Claiborne wall of the auditorium.

 

LIONS/LSU CLINIC BLDG 8TH FLOOR RENOVATIONS:

  • Facilities Services continued demolition of the conference and lobby areas.

 

MEB AIR HANDLING UNIT REPLACEMENT:

  • Facility Services continued monitoring temporary A/C units in the 4th and 5th Floor Quadrant B (corner of South Roman Street and Perdido Street ).
  • The contractor continued with the electrical and controls installation.   

 

MEB 4TH FLOOR MDL #4 RENOVATIONS:

  • The contractor removed the plastic containment and completed the cleaning for the abatement job. 

 

MEB 7th FLOOR PHYSIOLOGY LABS RENOVATIONS:

  • The contractor continued to tie-in the hot, cold, DI water, and drain lines in Rooms 7221, 7241, 7244, and 7250.
  • The contractor installed receptacles and cover plates in Rooms 7221, 7241, and 7250

 

RESOURCE CENTER ROOFING PROJECT:

  • The contractor installed tapered insulation and applied a two ply roofing system at all roof drains on the main penthouse.