Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, NOVEMBER 11, 2009

 

CITY PARK CAMPUS:

  • The contractor installed the top and bottom rail and the fence fabric for the third section of the chain link fence along Campus Road . 

 

RESOURCE CENTER ROOF REPLACEMENT:

  • The contractor replaced roof drains in both stairwell penthouses.
  • They started installing the framing for the parapet wall along the corner of Bolivar and Gravier St .
  • The flashing at the base of the atrium along the Gravier Street side of the roof was installed. 
  • The contractor replaced one additional row of glass panels in the atrium roof.  Seven out of fourteen rows have been completed.

 

MEB AIR HANDLING UNIT REPLACEMENT:

  • Facility Services continued installing temporary A/C in Quadrant D of the 2nd and 3rd Floors.
  • The contractor continued preparations for the demolition of AHU 3-D and 2-D.   

 

LIONS/LSU CLINIC BLDG 8TH FLOOR RENOVATIONS:

  • The contractor continued installing the HVAC ductwork in Dr. Bazans office and started the electrical rough-in.   

 

LIONS/LSU CLINIC BUILDING, NEUROBIOLOGY LAB RENOVATIONS:

  • The contractor continued removing interior walls. 

 

MEB MDL 4 RENOVATIONS:

  • The contractor continued raising the structural supports for the moveable partitions.
  • Workers began wall framing along the moveable partitions supports.
  • They continued the plumbing rough-in for Rooms 4215 and 4112.

 

MEB 2ND FLOOR AUTOPSY HVAC UPGRADE:

  • The contractor installed spiral ductwork in front of the procedure room.
  • They pulled electrical wires for the autopsy tables.

 

EXTERIOR/LANDSCAPING:

  • Facility Services conducted irrigation maintenance around the Downtown Campus.