Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, NOVEMBER 17, 2009

 

EXTERIOR/LANDSCAPING:

  • Facility Services continued installing irrigation piping at the corner of Bolivar St. and Poydras St.
  • The contractor continued installing new bollard lights around the T-lot. 
  • The contractor began construction of concrete curbs on Bolivar St. between Poydras St. and Perdido St .

 

MEB AIR HANDLING UNIT REPLACEMENT:

  • Facility Services continued monitoring the temporary A/C in Quadrant D of the 2nd and 3rd Floors.
  • The contractor completed the chilled water piping for AHU 2-D and continued installing ductwork, piping and electrical for AHU 2-D and 3-D.   

 

LIONS/LSU CLINIC BLDG 7TH FLOOR LAB RENOVATIONS:

  • The contractor continued the demolition.     

 

LIONS/LSU CLINIC BLDG 8TH FLOOR RENOVATIONS:

  • The contractor continued the electrical rough-in the Directors office area.   

 

MEB MDL 4 RENOVATIONS:

  • The contractor continued framing the wall and installed sheetrock along the moveable partitions supports.
  • The contractor continued roughing in the new plumbing below the 4th Floor.
  • The contractor roughed in the electrical wiring for the digital signage in the elevator lobby.