  • The contractor installed piping for the fan coil unit in Room 202A.
  • The contractor finished fine cleaning of the terrazzo floors and marble walls outside Room 203.
  • The contractor prepped the concrete landing for the flooring finish at the 1st Floor garage entrance.

 

FENCE REPLACEMENT PROJECT:

  • The contractor installed fence fabric along the DeSaix Subdivision.
  • Crews removed two trees near the Castine Street corner. 

 

EXTERIOR/LANDSCAPING:

  • Facility Services installed underground electrical conduit for the new bollard lighting adjacent to the South Roman Garage on Bolivar Street.
  • The contractor completed construction of the formwork for the new concrete curbs on Bolivar Street between Poydras Street and Perdido Street .

 

MEB AIR HANDLING UNIT REPLACEMENT:

  • Facility Services continued monitoring the temporary A/C in Quadrant D of the 2nd and 3rd Floors.
  • The contractor completed the chilled water piping on AHU 3-D.
  • The piping insulation was installed on the chilled water lines for AHU 2-D.
  • Crews continued installing ductwork, piping and electrical for AHU 2-D and 3-D.   

 

RESOURCE CENTER ROOF REPLACEMENT:

  • The contractor replaced the mechanical room roof drain and four roof drains on the atrium penthouse.
  • The contractor replaced the final row of atrium ceiling glass.

 

LIONS/LSU CLINIC BLDG 7TH FLOOR LAB RENOVATIONS:

  • The contractor continued demolition of sheetrock and wall framing.     

 

LIONS/LSU CLINIC BLDG 8TH FLOOR RENOVATIONS:

  • The contractor continued the electrical rough-in in the Directors office area.   

 

MEB MDL 4 RENOVATIONS:

  • The contractor installed new ceiling grid in the main MDL room
  • They installed the partition track in Room 4112A

 

MEB 2ND FLOOR AUTOPSY HVAC UPGRADE:

  • The contractor removed ceiling grid, tiles, and lights in the autopsy room.
  • Workers installed new ductwork above the cooler area