Monday, November 9, 2009

 

CITY PARK CAMPUS:

·       The contractor set the third and fourth sections of fence posts in the area from the staff parking lot to Castine Street, adjacent to the de Saix subdivision.

 

EXTERIOR/LANDSCAPING:

·       Facility Services prepared for possible high winds from Tropical Storm Ida at the Downtown, City Park and Uptown campuses.

 

MEB AIR HANDLING UNIT REPLACEMENT:

·       Facility Services continued installing the temporary A/C units in Quadrant D of the 2nd and 3rd Floors.

·       The contractor completed balancing and testing AHU 4-A and 5-A.

 

LIONS/LSU CLINIC BLDG. 8TH FLOOR RENOVATIONS:

·       The contractor continued framing the fur down in the large conference room and in the main lobby area.

·       They began installing the HVAC ductwork.

 

LIONS/LSU CLINIC BLDG. NEUROBIOLOGY LAB RENOVATIONS:

·       The contractor removed old flooring and sheetrock.

 

MEB AUTOPSY EXHAUST UPGRADE:

·       The contractor continued installing electrical conduit on the 1st Floor.

 

MEB MDL 4 RENOVATIONS:

·       The contractor rerouted condenser water piping and began installing structural supports for the moveable partitions.

 

RESIDENCE HALL LOBBY RENOVATIONS:

·       The contractor caulked the precast window sill.

 

RESOURCE CENTER ROOF REPLACEMENT:

·       The contractor secured all equipment and ceased work in anticipation of high winds from Tropical Storm Ida.