Louisiana State University Health Sciences Center Administration & Finance
 

THURSDAY, DECEMBER 10, 2009

 

1542 TULANE AVE. ADA ENTRANCE:

  • The contractor applied the first coat of paint on the floor. 

 

MEB AIR HANDLING UNIT REPLACEMENT:

  • Facility Services continued monitoring the temporary A/C units in Quadrant C of the 2nd and 3rd Floors.
  • The contractor completed demolition of duct work between AHU 2-B and Lecture Hall A.
  • They installed new variable air volume boxes for Lecture Hall A.
  • Their crews continued installation of the piping for AHU 3-C  and the electrical on AHU 2-C and AHU 3-C.
  • Others continued the duct work and exhaust fan installation preparations in mechanical room 2-A. 

 

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:

  • The contractor continued to rough in the power and run conduit for the large conference room. 

 

MEB MDL 4 RENOVATIONS:

  • The contractor ran new sprinkler pipe in Room 4210.
  • Workers continued installing light fixtures in the main MDL room and in Room 4215A.

 

MEB AUTOPSY HVAC UPGRADE:

  • The contractor roughed in the vacuum, hot and cold water lines on the 1st Floor.

 

RESIDENCE HALL WATER PROOFING:

  • The contractor removed old caulk and applied new waterproofing on the building elevation above the lobby expansion on the Perdido Street side. 
  • Caulking around the windows has been completed for 8 of 9 floors.

 

RESOURCE CENTER ROOF REPLACEMENT:

  • The contractor continued installing white cap sheet along the South Prieur Street side of the roof.

 

MEB SEMINAR ROOM AV INSTALLATION:

  • The contractor completed the installation of new A/V equipment in Seminar Room 5. 

 

EXTERIOR/LANDSCAPING:

  • Facility Services continued grading along Bolivar Street adjacent to the Residence Hall.