Louisiana State University Health Sciences Center Administration & Finance
 

FRIDAY, DECEMBER 11, 2009

 

1542 TULANE AVE. ADA ENTRANCE:

  • The contractor applied the second coat of paint to the floor. 

 

MEB AIR HANDLING UNIT REPLACEMENT:

  • Facility Services continued monitoring the temporary A/C in quadrant C of the 2nd and 3rd floors.
  • The contractor completed installation of the piping for AHU 3-C.
  • Crews continued the electrical installation on AHU 2-C and AHU 3-C.
  • They installed the new AHU 2-B and replaced the louver on mechanical room 2-B.
  • The contractor continued the duct work and exhaust fan installation in mechanical room 2-A.
  • They commenced repairs to the heating coils for AHU 6-C. 

 

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:

  • The contractor continued to rough in the power and run conduit for the large conference room. 

 

LIONS/LSU CLINIC BLDG 7th FLOOR RENOVATIONS:

  • The contractor installed studs for the laboratory walls.

 

MEB MDL 4 RENOVATIONS:

  • The contractor installed new sprinkler heads in Room 4210.

 

MEB AUTOPSY HVAC UPGRADE:

  • The contractor skim coated the soffit above the cooler doors and the chase wall inside the storage room.

 

RESIDENCE HALL WATER PROOFING:

  • The contractor completed waterproofing the exterior windows above the new roof on the Perdido Street side.

 

RESOURCE CENTER ROOF REPLACEMENT:

  • The contractor completed installing the white cap sheet on the main roof deck. 

 

DENTAL CLINIC WET VACCUM TANK REPLACEMENT:

  • The contractor installed the wash-down lines for the new tank.