Louisiana State University Health Sciences Center Administration & Finance
 

FRIDAY, DECEMBER 18, 2009

 

RESOURCE CENTER ROOF REPLACEMENT:

  • The contractor installed hat channel on the parapet wall on the South Prieur street side to support the parapet metal panels.

 

LIONS/LSU CLINIC BLDG 8TH FLOOR RENOVATIONS:

  • Facility Services completed running the drain lines for the break room. 

 

LIONS/LSU CLINIC BLDG 7th FLOOR RENOVATIONS:

  • The contractor continued roughing in electrical conduit and boxes for lighting.
  • Crews began installing the stud bracing

  

MEB AIR HANDLING UNIT REPLACEMENT:

  • Facility Services continued monitoring the temporary A/C units in Quadrant C of the 2nd and 3rd Floors.
  • The contractor continued installing the ductwork for AHU 2-B.
  • They completed the piping insulation on AHU 2-B.
  • Crews continued to test and balance AHU 2-C and AHU 3-C. 

 

MEB AUTOPSY HVAC UPGRADE:

  • The contractor continued installing supply HVAC duct in the Womens bathroom.

 

MEB 4TH FLOOR MDL 4 RENOVATIONS:

  • The contractor ran audio/visual wiring in the main MDL room.
  • Workers continued installing ceiling tiles in the main MDL room.
  • The wall in Room 4210 was taped and floated.

   

FENCE REPLACEMENT PROJECT:

  • The contractor installed the wire mesh for the fence at the Castine entrance and additional wire ties at the Castine Street and DeSaix Street entrances.