ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor is removing metal studs from the fire pump room.
  • Crews continued to remove construction material from the Bolivar Street side of the 1st Floor.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduit on the 1st Floor between the new switchgear location and riser B.

 LIONS/LSU CLINIC BLDG 7th FLOOR LAB RENOVATIONS:

  • The contractor continued installing hangers for the ceiling grid and patching sheetrock.
  • They installed a concrete pad for the transformer in the mechanical room and ran the emergency power electrical conduit in the mechanical room.

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:

  • The contractor installed sheetrock in the large conference room and started framing the curved storefront.

MEB AHU REPLACEMENT PROJECT:

  • Facility Services continued monitoring the temporary air conditioning serving the cafeteria kitchen area.
  • The contractor completed internal unit sealing and pipe labeling for all AHUs on the 4th, 5th, 6th and 7th Floors.

MEB MDL 4 RENOVATIONS:

  • The contractor terminated data ports in the storage rooms.

MEB 2ND FLOOR AUTOPSY HVAC UPGRADE:

  • The contractor completed installing block wall around the exhaust duct in the autopsy room.
  • They completed the installation of the first autopsy table.

RESIDENCE HALL FIRE ALARM UPGRADE:

  • The contractor continued installing and programming modules in the new fire alarm summary panel.
  • They began shifting the new alarm system devices from the old panel to the new panel.

EXTERIOR/LANDSCAPING:

  • Facility Services continued installing irrigation piping for the main lines on the field side of the horseshoe drive.