Louisiana State University Health Sciences Center Administration & Finance
 

MONDAY, JANUARY 4, 2010

LIONS/LSU CLINIC BLDG 7th FLOOR LAB RENOVATIONS:

  • The contractor continued to run electrical conduit above the ceiling.
  • Workers continued removing the interior wall.

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:

  • The contractor continued running lighting conduit and pulling wires.

MEB AIR HANDLING UNIT REPLACEMENT:

  • The contractor completed duct work, electrical piping, and insulation for AHU 2-B.
  • They continue the installation of the duct detector for AHU 2-B.
  • The contractor completed installation of duct work for AHU 2-D.
  • Crews installed isolator springs on the exhaust fan for AHU 4-A.

MEB MDL 4 RENOVATIONS:

  • The contractor continued connecting medical air/gas/vac lines to the new lab furniture.
  • Network cables were run to the new lab furniture.

MEB MORGUE HVAC UPGRADE:

  • The contractor insulated the HVAC duct in the Womens bathroom.
  • Workers installed ceiling tiles in the autopsy room.

MEB SEMINAR ROOMS:

  • The contractor continued patching the sheetrock wall in Seminar Room 4.
  • They continued installing A/V equipment and podiums in other seminar rooms.

RESOURCE CENTER ROOF REPLACEMENT:

  • The contractor completed the wall panel installation except for sections near both roof penthouses.
  • Crews installed the counter-flashing around the atrium and started installing the counter-flashing along Gravier Street.
  • They installed the parapet wall cap on the Tulane Street stairwell penthouse.