Louisiana State University Health Sciences Center Administration & Finance
 

MONDAY, FEBRUARY 1, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor removed sheetrock from Stairwell 2 and continued removing debris from the Bolivar St. side of the building.
  • Demolition is underway in the Tiger Room.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor removed restroom fixtures from the 1st Floor. ¬∑Crews continued installing conduit on the 1st Floor between the new switchgear location and riser B.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor installed a temporary fence in the back parking lot area surrounding the construction site.

MEB MDL 4 RENOVATIONS:

  • The renovations are substantially complete. The contractor began working on the punch list items.

LIONS/LSU CLINIC BLDG 7th FLOOR LAB RENOVATIONS:

  • The contractor continued installing hangers for the ceiling grid and patching sheetrock.
  • Workers installed emergency power electrical conduit in the mechanical room.
  • They ran heating hot water pipes to the VAV boxes.

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:

  • The contractor continued framing the curved storefront wall.
  • Facility Services ran heating hot water pipes to the VAV boxes.

MEB AHU REPLACEMENT PROJECT:

  • Facility Services removed the temporary air conditioning serving the cafeteria kitchen area.
  • The contractor completed pipe labeling for all AHUs on the 2nd and 3rd floors.

RESIDENCE HALL FIRE ALARM UPGRADE:

  • The contractor continued installing and programming modules in the new fire alarm summary panel and shifting the new devices from the old panel to the new panel.

EXTERIOR/LANDSCAPING:

  • Facility Services completed installing irrigation control valves and piping for the main lines on the field side of the horseshoe drive.