Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, FEBRUARY 10, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:
  • The contractor ran electrical conduit for the light fixtures on the west side of the 1st Floor.
  • Crews removed the duct detectors from the AHUs on the 1st Floor.
  • The ceilings were removed from Rooms 2B2 and 2B4.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
  • The contractor continued installing conduit on the 1st Floor between the new switchgear location and the tap box in Room 219.

LIONS/LSU CLINIC BLDG 7th FLOOR LAB RENOVATIONS:
  • The contractor removed the wall adjacent to the lab to make room for the window.

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:
  • The contractor taped and floated the sheetrock in the large and small conference rooms.
  • Workers installed electrical receptacles for the 56 inch LCDs in the Director’s office.

MEB 2ND FLOOR AUTOPSY HVAC UPGRADE:
  • The contractor completed the installation of the second autopsy table and connected the plumbing and electrical.

RESIDENCE HALL LOBBY ROOF FLASHING:
  • The contractor installed sheetrock in apartment B34.

RESIDENCE HALL FIRE ALARM UPGRADE:
  • The contractor continued programming modules in the new fire alarm summary panel and installed new smoke detectors in the elevator shafts.

FENCE REPLACEMENT PROJECT:
  • The contractor installed framing and rebar for 10 of 35 monumental fence columns.

EXTERIOR/LANDSCAPING:
  • Facility Services completed the irrigation station piping and sprinkler heads along the Clinic side of the horseshoe drive.
  • They installed piping for first of two stations in the center island.