WEDNESDAY, FEBRUARY 17, 2010ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION: · The contractor continued removing sheetrock and ceilings in Rooms 245 and 256. · They installed electrical conduit in Rooms 2B2 and 2B4. RESOURCE CENTER PERMANENT REPAIRS & MITIGATION: · The contractor continued installing conduit on the 1st Floor near the Womens restroom. LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS: · The contractor taped, floated and primed the sheetrock in the large and small conference rooms. RESIDENCE HALL LOBBY ROOF FLASHING: · The contractor cut the exterior wall and installed metal flashing in apartment C34. RESIDENCE HALL FIRE ALARM UPGRADE: · The contractor continued programming modules in the new fire alarm summary panel. · They completed transferring flow and tamper switches for all three towers to the new panel. EXTERIOR/LANDSCAPING: · Facility Services continued installing pipe and sprinklers for the irrigation station that will cover the planting area in the horseshoe drive median. |