ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

·         The contractor removed tiles from the 1st Floor bathrooms near the switchgear.

·         They pulled wire for the 1st Floor lights on the Bolivar Street side of the building.

 

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

·         The contractor continued installing conduit on the 1st Floor from the new switchgear room to the new ATS room.

·         Workers began laying out the new walls in the mail processing area.

 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

·         The contractor surveyed and marked the parking area in preparation for the pile driving.

 

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:

·         The contractor painted the fur down in the lobby area.  

 

LIONS/LSU CLINIC BLDG 7th FLOOR RENOVATIONS:

·         The contractor pulled wires for lighting and receptacles in the renovated spaces.

 

RESIDENCE HALL FIRE ALARM UPGRADE:

·         Contractor completed installation of fire devices in the 1st Floor fire pump room.

 

MORGUE RENOVATIONS:

·         The contractor powered the exhaust fans on the roof and continued working on punch list

 

EXTERIOR/LANDSCAPING:

·         Facility Services continued removing old vegetation from the center island of the horseshoe drive and installed irrigation station piping on the Florida Avenue side of the Clinic Building.