Louisiana State University Health Sciences Center Administration & Finance
 

FRIDAY, MARCH 26, 2010

 

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

·         The contractor ran conduit to panel XLB2.

·         Crews continued refurbishing the AHUs on the 1st Floor.  

 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

·         The contractor completed excavations for all 8 pile caps.

·         They built the concrete forms and set steel bars for 6 of the pile caps.

 

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

·         The contractor completed enlarging the floor penetrations for the electrical risers.

 

LIONS/LSU CLINIC BLDG 7th FLOOR RENOVATIONS:

·         The contractor painted the walls and door frames.

 

CEB COVERED WALKWAY:

·         The contractor continued demolition of the Lakeside lot awning.   

 

EXTERIOR/LANDSCAPING:

·         Facility Services completed installing new sprinkler heads in the patio courtyard and buried all new irrigation lines.